Status Date Overall Project Status Project Officer Contact
15 Jun 2024 Package-I-28 % completed, 193 nos FHTCs are given,Total Pipe laid till date-3860 m (FHTCS and pipe laying in progress . Package-II-66 % completed , 2093 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-66 % completed , 775 nos FHTCs are given, Total Pipe laid till date- 12300 m . Kollam WS Sn 2 - AE
14 Jun 2024 Package-I-28 % completed, 193 nos FHTCs are given,Total Pipe laid till date-3860 m (FHTCS and pipe laying in progress . Package-II-66 % completed , 2093 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-65 % completed , 759 nos FHTCs are given, Total Pipe laid till date- 12300 m . Kollam WS Sn 2 - AE
10 Jun 2024 Package-I-28 % completed, 193 nos FHTCs are given,Total Pipe laid till date-3860 m (FHTCS and pipe laying in progress . Package-II-53 % completed , 1645 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-65 % completed , 747 nos FHTCs are given, Total Pipe laid till date- 12300 m -Restoration of road by laying concrete concrete under progress. Continuous Heavy rain and water logged areas excavation cannot possible. Hence now no work at sites. Kollam WS Sn 2 - AE
04 Jun 2024 Package-I-28 % completed, 193 nos FHTCs are given,Total Pipe laid till date-3860 m (FHTCS and pipe laying in progress . Package-II-53 % completed , 1645 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-65 % completed , 747 nos FHTCs are given, Total Pipe laid till date- 12300 m -Restoration of road by laying concrete concrete under progress. Continuous Heavy rain and water logged areas excavation cannot possible. Hence now no work at sites. Kollam WS Sn 2 - AE
01 Jun 2024 Package-I-28 % completed, 193 nos FHTCs are given,Total Pipe laid till date-3860 m (FHTCS and pipe laying in progress . Package-II-51 % completed , 1607 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-65 % completed , 747 nos FHTCs are given, Total Pipe laid till date- 12300 m -Restoration of road by laying concrete concrete under progress. Continuous Heavy rain and water logged areas excavation cannot possible. Hence now no work at sites.. Kollam WS Sn 2 - AE
28 May 2024 Package-I-28 % completed, 193 nos FHTCs are given,Total Pipe laid till date-3860 m (FHTCS and pipe laying in progress . Package-II-51 % completed , 1607 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-65 % completed , 747 nos FHTCs are given, Total Pipe laid till date- 12300 m -Restoration of road by laying concrete concrete under progress. Continuous Heavy rain affects the progress of work. Kollam WS Sn 2 - AE
25 May 2024 Package-I-28 % completed, 193 nos FHTCs are given,Total Pipe laid till date-3860 m (FHTCS and pipe laying in progress . Package-II-51 % completed , 1607 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-65 % completed , 747 nos FHTCs are given, Total Pipe laid till date- 12300 m -Restoration of road by laying concrete concrete under progress. Heavy rain affects the progress of work. Kollam WS Sn 2 - AE
21 May 2024 Package-I-26 % completed, 185 nos FHTCs are given,Total Pipe laid till date-3520 m (FHTCS and pipe laying in progress . Package-II-51 % completed , 1607 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-65 % completed , 747 nos FHTCs are given, Total Pipe laid till date- 12300 m -Restoration of road by laying concrete concrete under progress. Heavy rain affects the progress of work. Kollam WS Sn 2 - AE
17 May 2024 Package-I-26 % completed, 185 nos FHTCs are given,Total Pipe laid till date-3520 m (FHTCS and pipe laying in progress . Package-II-50 % completed , 1512 FHTCs are given, Total Pipe laid till date-9000 m(FHTCS and pipe laying in progress ) -- Package-III-65 % completed , 724 nos FHTCs are given, Total Pipe laid till date- 12300 m -Restoration of road by laying concrete concrete under progress. Kollam WS Sn 2 - AE
13 May 2024 Package-I-26 % completed, 185 nos FHTCs are given,Total Pipe laid till date-3520 m (FHTCS and pipe laying in progress . Package-II-48 % completed , 1449 FHTCs are given, Total Pipe laid till date-8231m(FHTCS and pipe laying in progress ) -- Package-III-64 % completed , 698 nos FHTCs are given, Total Pipe laid till date- 12150 m -Restoration of road by laying concrete concrete under progress. Kollam WS Sn 2 - AE