| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 15 Jun 2024 | Package-I-28 % completed, 193 nos FHTCs are given,Total Pipe laid till date-3860 m (FHTCS and pipe laying in progress . Package-II-66 % completed , 2093 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-66 % completed , 775 nos FHTCs are given, Total Pipe laid till date- 12300 m . | Kollam WS Sn 2 - AE | |
| 14 Jun 2024 | Package-I-28 % completed, 193 nos FHTCs are given,Total Pipe laid till date-3860 m (FHTCS and pipe laying in progress . Package-II-66 % completed , 2093 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-65 % completed , 759 nos FHTCs are given, Total Pipe laid till date- 12300 m . | Kollam WS Sn 2 - AE | |
| 10 Jun 2024 | Package-I-28 % completed, 193 nos FHTCs are given,Total Pipe laid till date-3860 m (FHTCS and pipe laying in progress . Package-II-53 % completed , 1645 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-65 % completed , 747 nos FHTCs are given, Total Pipe laid till date- 12300 m -Restoration of road by laying concrete concrete under progress. Continuous Heavy rain and water logged areas excavation cannot possible. Hence now no work at sites. | Kollam WS Sn 2 - AE | |
| 04 Jun 2024 | Package-I-28 % completed, 193 nos FHTCs are given,Total Pipe laid till date-3860 m (FHTCS and pipe laying in progress . Package-II-53 % completed , 1645 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-65 % completed , 747 nos FHTCs are given, Total Pipe laid till date- 12300 m -Restoration of road by laying concrete concrete under progress. Continuous Heavy rain and water logged areas excavation cannot possible. Hence now no work at sites. | Kollam WS Sn 2 - AE | |
| 01 Jun 2024 | Package-I-28 % completed, 193 nos FHTCs are given,Total Pipe laid till date-3860 m (FHTCS and pipe laying in progress . Package-II-51 % completed , 1607 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-65 % completed , 747 nos FHTCs are given, Total Pipe laid till date- 12300 m -Restoration of road by laying concrete concrete under progress. Continuous Heavy rain and water logged areas excavation cannot possible. Hence now no work at sites.. | Kollam WS Sn 2 - AE | |
| 28 May 2024 | Package-I-28 % completed, 193 nos FHTCs are given,Total Pipe laid till date-3860 m (FHTCS and pipe laying in progress . Package-II-51 % completed , 1607 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-65 % completed , 747 nos FHTCs are given, Total Pipe laid till date- 12300 m -Restoration of road by laying concrete concrete under progress. Continuous Heavy rain affects the progress of work. | Kollam WS Sn 2 - AE | |
| 25 May 2024 | Package-I-28 % completed, 193 nos FHTCs are given,Total Pipe laid till date-3860 m (FHTCS and pipe laying in progress . Package-II-51 % completed , 1607 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-65 % completed , 747 nos FHTCs are given, Total Pipe laid till date- 12300 m -Restoration of road by laying concrete concrete under progress. Heavy rain affects the progress of work. | Kollam WS Sn 2 - AE | |
| 21 May 2024 | Package-I-26 % completed, 185 nos FHTCs are given,Total Pipe laid till date-3520 m (FHTCS and pipe laying in progress . Package-II-51 % completed , 1607 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-65 % completed , 747 nos FHTCs are given, Total Pipe laid till date- 12300 m -Restoration of road by laying concrete concrete under progress. Heavy rain affects the progress of work. | Kollam WS Sn 2 - AE | |
| 17 May 2024 | Package-I-26 % completed, 185 nos FHTCs are given,Total Pipe laid till date-3520 m (FHTCS and pipe laying in progress . Package-II-50 % completed , 1512 FHTCs are given, Total Pipe laid till date-9000 m(FHTCS and pipe laying in progress ) -- Package-III-65 % completed , 724 nos FHTCs are given, Total Pipe laid till date- 12300 m -Restoration of road by laying concrete concrete under progress. | Kollam WS Sn 2 - AE | |
| 13 May 2024 | Package-I-26 % completed, 185 nos FHTCs are given,Total Pipe laid till date-3520 m (FHTCS and pipe laying in progress . Package-II-48 % completed , 1449 FHTCs are given, Total Pipe laid till date-8231m(FHTCS and pipe laying in progress ) -- Package-III-64 % completed , 698 nos FHTCs are given, Total Pipe laid till date- 12150 m -Restoration of road by laying concrete concrete under progress. | Kollam WS Sn 2 - AE |