Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Feb 2024 Package-I-11 % completed ,45 nos FHTCs are given,Total Pipe laid till date-2300m (FHTCS and pipe laying in progress . Package-II-30% completed ,560 nos FHTCs are given,Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-43% completed ,295 nos FHTCs are given,Total Pipe laid till date- 9670 m - Work in progress Kollam WS Sn 2 - AE
21 Feb 2024 Package-I-11 % completed ,45 nos FHTCs are given,Total Pipe laid till date-2300m (FHTCS and pipe laying in progress . Package-II-30% completed ,560 nos FHTCs are given,Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-43% completed ,294 nos FHTCs are given,Total Pipe laid till date- 9670 m - Work in progress Kollam WS Sn 2 - AE
21 Feb 2024 Package-I-11 % completed ,45 nos FHTCs are given,Total Pipe laid till date-2300m (FHTCS and pipe laying in progress . Package-II-30% completed ,560 nos FHTCs are given,Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-43% completed ,294 nos FHTCs are given,Total Pipe laid till date- 9670 m - Work in progress Kollam WS Sn 2 - AE
17 Feb 2024 Package-I-11 % completed ,35 nos FHTCs are given,Total Pipe laid till date-2250m (FHTCS and pipe laying in progress . Package-II-27% completed ,453 nos FHTCs are given,Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-42% completed ,294 nos FHTCs are given,Total Pipe laid till date- 9461 m - Work in progress Kollam WS Sn 2 - AE
14 Feb 2024 Package-I-11 % completed ,35 nos FHTCs are given,Total Pipe laid till date-2250m (FHTCS and pipe laying in progress . Package-II-27% completed ,453 nos FHTCs are given,Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-42% completed ,294 nos FHTCs are given,Total Pipe laid till date- 9461 m - Work in progress Kollam WS Sn 2 - AE
12 Feb 2024 Package-I-11 % completed ,35 nos FHTCs are given,Total Pipe laid till date-2250m (FHTCS and pipe laying in progress . Package-II-27% completed ,453 nos FHTCs are given,Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-41% completed ,266 nos FHTCs are given,Total Pipe laid till date- 9461 m - Work in progress Kollam WS Sn 2 - AE
06 Feb 2024 Package-I-11 % completed ,35 nos FHTCs are given,Total Pipe laid till date-2250m (FHTCS and pipe laying in progress . Package-II-21% completed ,358 nos FHTCs are given,Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-39% completed ,257 nos FHTCs are given,Total Pipe laid till date- 8855 m - Work in progress Kollam WS Sn 2 - AE
02 Feb 2024 Package-I-11 % completed ,35 nos FHTCs are given,Total Pipe laid till date-2250m (FHTCS and pipe laying in progress . Package-II-20% completed ,340 nos FHTCs are given,Total Pipe laid till date-7592m(FHTCS and pipe laying in progress ) -- Package-III-39% completed ,247 nos FHTCs are given,Total Pipe laid till date- 8750 m - Work in progress Kollam WS Sn 2 - AE
29 Jan 2024 Package-I-9 % completed ,26 nos FHTCs are given,Total Pipe laid till date-1985m (FHTCS and pipe laying in progress . Package-II-14% completed ,258 nos FHTCs are given,Total Pipe laid till date-7592m(FHTCS and pipe laying in progress ) -- Package-III-25% completed ,207 nos FHTCs are given,Total Pipe laid till date- 8550 m - Work in progress Kollam WS Sn 2 - AE
23 Jan 2024 Package-I-9 % completed ,23 nos FHTCs are given,Total Pipe laid till date-1850m (FHTCS and pipe laying in progress . Package-II-13% completed ,180 nos FHTCs are given,Total Pipe laid till date-7592m(FHTCS and pipe laying in progress ) -- Package-III-25% completed ,202 nos FHTCs are given,Total Pipe laid till date- 8550 m - Two part bills ( for 137 nos. of FHTCS and 8210 m pipe laying ) submitted. Work in progress. Kollam WS Sn 2 - AE