02 Nov 2024 Package-1-Old Muncipal area in Kollam corporation - 42 % completed, 460 nos FHTCs are given,Total Pipe laid till date-5100 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 71 % completed ,1066 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 79 % completed , 3066 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). Kollam WS Sn 2 - AE
30 Oct 2024 Package-1- Sakthikulangara & Thrikkadavoor zone - 71 % completed ,1066 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-II-Vadakkevila- Eravipuram & Kilikolloor zone - 79 % completed , 3037 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). Package-3-Old Muncipal area in Kollam corporation - 42 % completed, 450 nos FHTCs are given,Total Pipe laid till date-5051 m (Work in progress) . Kollam WS Sn 2 - AE
28 Oct 2024 Package-1- Sakthikulangara & Thrikkadavoor zone - 71 % completed ,1066 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-II-Vadakkevila- Eravipuram & Kilikolloor zone - 79 % completed , 3013 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). Package-3-Old Muncipal area in Kollam corporation - 42 % completed, 450 nos FHTCs are given,Total Pipe laid till date-5051 m (Work in progress) . Kollam WS Sn 2 - AE
28 Oct 2024 Package-I-42 % completed, 450 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-III-79 % completed , 3013 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ) -- Package-II-71 % completed ,1066 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed). Kollam WS Sn 2 - AE
25 Oct 2024 Package-I-42 % completed, 450 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-III-79 % completed , 3013 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ) -- Package-II-71 % completed ,1066 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed). Kollam WS Sn 2 - AE
22 Oct 2024 Package-I-40 % completed, 400 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-III-78 % completed , 3013 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ) -- Package-II-71 % completed ,1066 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed). Kollam WS Sn 2 - AE
18 Oct 2024 Package-I-36 % completed, 360 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-III-78 % completed , 2955 FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ) -- Package-II-71 % completed ,1066 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed). Kollam WS Sn 2 - AE
14 Oct 2024 Package-I-36 % completed, 360 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-III-78 % completed , 2945 FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ) -- Package-II-71 % completed ,1066 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed). Kollam WS Sn 2 - AE
08 Oct 2024 Package-I-36 % completed, 360 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-III-78 % completed , 2936 FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ) -- Package-II-71 % completed ,1066 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed). Kollam WS Sn 2 - AE
04 Oct 2024 Package-I-36 % completed, 360 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-III-78 % completed , 2936 FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ) -- Package-II-71 % completed ,1066 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed. Kollam WS Sn 2 - AE