Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

AMRUT-2.0-RETROFITTING AND PROVIDING NEW WATER CONNECTIONS IN KOLLAM CORPORATION

Project AMRUT-2.0-RETROFITTING AND PROVIDING NEW WATER CONNECTIONS IN KOLLAM CORPORATION
Project Code KLMAMRUT112213823
Type Main project
Funding Agency AMRUT
Category AMRUT 2
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-2.0-RETROFITTING AND PROVIDING NEW WATER CONNECTIONS AT OLD MUNICIPAL AREA IN KOLLAM CORPORATION
Status On-going
District Kollam
Executing Office Kollam PH Dn
AS Amount (Rs) 220000000
AS Number G.O.(Rt)No.2906/2022/LSGD
TS Amount (Rs) 200000000
TS Number WRD/KWA-CE(SR)/EST_TS/1091/2022_26_1_1 Dated: 19-01-2023
Total Bill Submitted (Rs) 58961125
Total Bill Paid (Rs) 0
Population Benefitted 40350
Capacity in MLD 11.00
Actual Project Completion Date 31 Mar 2025
Coverage 55 Divisions in Kollam corporation
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 AMRUT- 2.0 RETROFIT AND PROVIDING NEW WATER CONNECTION AT SAKTHIKULANGARA AND THRIKKADAVOOR AREA UNDER KOLLAM CORPORATION-AMRUT- 2.0 RETROFIT AND PROVIDING NEW WATER CONNECTION AT SAKTHIKULANGARA AND THRIKKADAVOOR AREAS UNDER KOLLAM CORPORATION Kollam WS Sn 2
2 AMRUT- 2.0 - RETROFIT AND PROVIDING NEW WATER CONNECTION AT VADAKKEVILA, ERAVIPURAM & KILIKOLLOOR AREA UNDER KOLLAM CORPORATION Kollam WS Sn 3
3 AMRUT-2.0-RETROFITTING AND PROVIDING NEW WATER CONNECTIONS AT OLD MUNCIPAL AREA IN KOLLAM CORPORATION Kollam WS Sn 1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 Oct 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1520 nos FHTCs are given,Total Pipe laid till date-13899.5m Work is ongoing. ----- Package-3- Sakthikulangara & Thrikkadavoor zone - 93 % completed ,2159 nos FHTCs are given, Total Pipe laid till date- 17275.9 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, -----------------Package 2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5929 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
01 Oct 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1520 nos FHTCs are given,Total Pipe laid till date-13899.5m Work is ongoing. ----- Package-3- Sakthikulangara & Thrikkadavoor zone - 93 % completed ,2147 nos FHTCs are given, Total Pipe laid till date- 17275.9 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, Beneficiary list form corporation is delaying , this will affect the completion of the work . -----------------Package 2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5929 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
19 Sep 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1520 nos FHTCs are given,Total Pipe laid till date-13899.5m Work is ongoing. ----- Package-3- Sakthikulangara & Thrikkadavoor zone - 93 % completed ,2140 nos FHTCs are given, Total Pipe laid till date- 17275.9 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, Beneficiary list form corporation is delaying , this will affect the completion of the work . -----------------Package 2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5889 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
14 Sep 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1520 nos FHTCs are given,Total Pipe laid till date-13899.5m Work is ongoing. ----- Package-3- Sakthikulangara & Thrikkadavoor zone - 93 % completed ,2140 nos FHTCs are given, Total Pipe laid till date- 17275.9 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, Beneficiary list form corporation is delaying , this will affect the completion of the work . -----------------Package 2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5888 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
11 Sep 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1520 nos FHTCs are given,Total Pipe laid till date-13899.5m Work is ongoing. ----- Package-3- Sakthikulangara & Thrikkadavoor zone - 93 % completed ,2140 nos FHTCs are given, Total Pipe laid till date- 17275.9 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, Beneficiary list form corporation is delaying , this will affect the completion of the work . -----------------Package 2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5888 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 17/05/2023
Scheduled date of Completion of the Project 08 May 2024
Expected date of Completion 30/11/2024

Processing Dates

AS Date 24 Nov 2022
TS Date 19 Jan 2023

Other details

Project Officers View