Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 Oct 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1520 nos FHTCs are given,Total Pipe laid till date-13899.5m Work is ongoing. ----- Package-3- Sakthikulangara & Thrikkadavoor zone - 93 % completed ,2159 nos FHTCs are given, Total Pipe laid till date- 17275.9 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, -----------------Package 2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5929 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
01 Oct 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1520 nos FHTCs are given,Total Pipe laid till date-13899.5m Work is ongoing. ----- Package-3- Sakthikulangara & Thrikkadavoor zone - 93 % completed ,2147 nos FHTCs are given, Total Pipe laid till date- 17275.9 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, Beneficiary list form corporation is delaying , this will affect the completion of the work . -----------------Package 2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5929 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
19 Sep 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1520 nos FHTCs are given,Total Pipe laid till date-13899.5m Work is ongoing. ----- Package-3- Sakthikulangara & Thrikkadavoor zone - 93 % completed ,2140 nos FHTCs are given, Total Pipe laid till date- 17275.9 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, Beneficiary list form corporation is delaying , this will affect the completion of the work . -----------------Package 2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5889 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
14 Sep 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1520 nos FHTCs are given,Total Pipe laid till date-13899.5m Work is ongoing. ----- Package-3- Sakthikulangara & Thrikkadavoor zone - 93 % completed ,2140 nos FHTCs are given, Total Pipe laid till date- 17275.9 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, Beneficiary list form corporation is delaying , this will affect the completion of the work . -----------------Package 2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5888 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
11 Sep 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1520 nos FHTCs are given,Total Pipe laid till date-13899.5m Work is ongoing. ----- Package-3- Sakthikulangara & Thrikkadavoor zone - 93 % completed ,2140 nos FHTCs are given, Total Pipe laid till date- 17275.9 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, Beneficiary list form corporation is delaying , this will affect the completion of the work . -----------------Package 2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5888 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
08 Sep 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1520 nos FHTCs are given,Total Pipe laid till date-13899.5m Work is ongoing. ----- Package-3- Sakthikulangara & Thrikkadavoor zone - 93 % completed ,2140 nos FHTCs are given, Total Pipe laid till date- 17275.9 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, Beneficiary list form corporation is delaying , this will affect the completion of the work . -----------------Package 2 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5888 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
31 Aug 2026 ackage-1- Old Muncipal area in Kollam corporation - 95% completed, 1520 nos FHTCs are given,Total Pipe laid till date-13899.5m Work is ongoing. ----- Package-3- Sakthikulangara & Thrikkadavoor zone - 93 % completed ,2140 nos FHTCs are given, Total Pipe laid till date- 16041 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, heavy rain and water logging cause slight delay in work . -----------------Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5888 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
24 Aug 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1520 nos FHTCs are given,Total Pipe laid till date-13825.1m Work is ongoing. ----- Package-3- Sakthikulangara & Thrikkadavoor zone - 93 % completed ,2131 nos FHTCs are given, Total Pipe laid till date- 16041 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, heavy rain and water logging cause slight delay in work . -----------------Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5865 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
13 Aug 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1520 nos FHTCs are given,Total Pipe laid till date-13825.1m Work is ongoing. ----- Package-3- Sakthikulangara & Thrikkadavoor zone - 93 % completed ,2112 nos FHTCs are given, Total Pipe laid till date- 16041 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, heavy rain and water logging cause slight delay in work . -----------------Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5847 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE
18 Jul 2026 Package-1- Old Muncipal area in Kollam corporation - 95% completed, 1452 nos FHTCs are given,Total Pipe laid till date-13825.1m Work is ongoing. ----- Package-2- Sakthikulangara & Thrikkadavoor zone - 92 % completed ,2094 nos FHTCs are given, Total Pipe laid till date- 15727.8 m(laying completed), FHTC works and additional pipe laying works for giving maximum FHTCS are ongoing, heavy rain and water logging cause slight delay in work . Package 3 -Vadakkevila- Eravipuram & Kilikolloor zone - 99 % completed , 5806 nos FHTCs are completed. Total Pipe laid till date-13617.5 m Kollam WS Sn 2 - AE