| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 20 Jan 2024 | Package-I-8% completed ,18 nos FHTCs are given,Total Pipe laid till date-1750m (FHTCS and pipe laying in progress . Package-II-13% completed ,180 nos FHTCs are given,Total Pipe laid till date-7592m(FHTCS and pipe laying in progress ) -- Package-III-24% completed ,185 nos FHTCs are given,Total Pipe laid till date- 8550 m - Two part bills ( for 137 nos. of FHTCS and 8210 m pipe laying ) submitted. Work in progress. | Kollam WS Sn 2 - AE | |
| 16 Jan 2024 | Package-I-8% completed ,18 nos FHTCs are given,Total Pipe laid till date-1750m (FHTCS and pipe laying in progress . Package-II-10% completed ,118 nos FHTCs are given,Total Pipe laid till date-7592m(FHTCS and pipe laying in progress ) -- Package-III-24% completed ,185 nos FHTCs are given,Total Pipe laid till date- 8550 m - Two part bills ( for 137 nos. of FHTCS and 8210 m pipe laying ) submitted. Work in progress. | Kollam WS Sn 2 - AE | |
| 09 Jan 2024 | Package-I-8% completed ,18 nos FHTCs are given,Total Pipe laid till date-1750m (FHTCS and pipe laying in progress . Package-II-8% completed ,65 nos FHTCs are given,Total Pipe laid till date-6592m(FHTCS and pipe laying in progress ) -- Package-III-22% completed ,147nos FHTCs are given,Total Pipe laid till date-8330 m - Two part bills submitted. ( FHTC works and pipe laying in progress) | Kollam WS Sn 2 - AE | |
| 06 Jan 2024 | Package-I-6% completed ,15 nos FHTCs are given,Total Pipe laid till date-1690m Package-II-6% completed ,65 nos FHTCs are given,Total Pipe laid till date-6592m( pipe laying in progress ) -- Package-III-21% completed ,137nos FHTCs are given,Total Pipe laid till date-8210m - Two part bills submitted. ( pipe laying in progress) | Kollam WS Sn 2 - AE | |
| 03 Jan 2024 | Package-I-6% completed ,15 nos FHTCs are given,Total Pipe laid till date-1690m Package-II-6% completed ,65 nos FHTCs are given,Total Pipe laid till date-6592m( pipe laying in progress ) -- Package-III-21% completed ,137nos FHTCs are given,Total Pipe laid till date-8210m( pipe laying in progress) | Kollam WS Sn 2 - AE | |
| 29 Dec 2023 | Package-I-6% completed ,15 nos FHTCs are given,Total Pipe laid till date-1690m Package-II-6% completed ,20 nos FHTCs are given,Total Pipe laid till date-6592m-- Package-III-21% completed ,137nos FHTCs are given,Total Pipe laid till date-8210m | Kollam WS Sn 2 - AE | |
| 28 Dec 2023 | Package-I-6% completed ,15 nos FHTCs are given,Total Pipe laid till date-1690m Package-II-6% completed ,20 nos FHTCs are given,Total Pipe laid till date-6592m-- Package-III-19% completed ,137nos FHTCs are given,Total Pipe laid till date-8210m | Kollam WS Sn 2 - AE | |
| 28 Dec 2023 | Package-I-6% completed ,15 nos FHTCs are given,Total Pipe laid till date-1690m Package-II-19% completed ,137nos FHTCs are given,Total Pipe laid till date-8210m Package-III-6% completed ,20 nos FHTCs are given,Total Pipe laid till date-6592m-- | Kollam PH Dn EE | |
| 26 Dec 2023 | Package-1 pipe laying work ongoing, Package-2 pipe laying work ongoing, Package-3 - Pipe laying Work is ongoing | Kollam WS Sn 2 - AE | |
| 22 Dec 2023 | Package-1 pipe laying work ongoing, Package-2 pipe laying work ongoing, Package-3 - Pipe laying Work in progress | Kollam WS Sn 2 - AE |