| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Apr 2024 | Package-I-20 % completed, 117 nos FHTCs are given,Total Pipe laid till date-3000m (FHTCS and pipe laying in progress . Package-II-41 % completed , 1153 FHTCs are given, Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-545 % completed ,471 nos FHTCs are given, Total Pipe laid till date- 11350 m - Work in progress | Kollam WS Sn 2 - AE | |
| 01 Apr 2024 | Package-I-19 % completed, 106 nos FHTCs are given,Total Pipe laid till date-3000m (FHTCS and pipe laying in progress . Package-II-40 % completed , 1098 FHTCs are given, Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-54 % completed ,426 nos FHTCs are given, Total Pipe laid till date- 11188 m - Work in progress | Kollam WS Sn 2 - AE | |
| 01 Apr 2024 | Package-I-19 % completed, 97 nos FHTCs are given,Total Pipe laid till date-3000m (FHTCS and pipe laying in progress . Package-II-40 % completed , 1098 FHTCs are given, Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-54 % completed ,426 nos FHTCs are given, Total Pipe laid till date- 11188 m - Work in progress | Kollam WS Sn 2 - AE | |
| 25 Mar 2024 | Package-I-19 % completed, 97 nos FHTCs are given,Total Pipe laid till date-3000m (FHTCS and pipe laying in progress . Package-II-40 % completed , 1098 FHTCs are given, Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-54 % completed ,426 nos FHTCs are given, Total Pipe laid till date- 11188 m - Work in progress | Kollam WS Sn 2 - AE | |
| 21 Mar 2024 | Package-I-19 % completed, 90 nos FHTCs are given,Total Pipe laid till date-3000m (FHTCS and pipe laying in progress . Package-II-39% completed , 1064 FHTCs are given, Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-53 % completed ,422 nos FHTCs are given,Total Pipe laid till date- 11171 m - Work in progress | Kollam WS Sn 2 - AE | |
| 15 Mar 2024 | Package-I-18 % completed, 70 nos FHTCs are given,Total Pipe laid till date-3000m (FHTCS and pipe laying in progress . Package-II-36% completed ,760 FHTCs are given,Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-49% completed ,341 nos FHTCs are given,Total Pipe laid till date- 10500 m - Work in progress | Kollam WS Sn 2 - AE | |
| 11 Mar 2024 | Package-I-18 % completed, 70 nos FHTCs are given,Total Pipe laid till date-3000m (FHTCS and pipe laying in progress . Package-II-35% completed ,760 FHTCs are given,Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-45% completed ,316 nos FHTCs are given,Total Pipe laid till date- 10000 m - Work in progress | Kollam WS Sn 2 - AE | |
| 06 Mar 2024 | Package-I-17 % completed, 62 nos FHTCs are given,Total Pipe laid till date-3000m (FHTCS and pipe laying in progress . Package-II-34% completed ,760 FHTCs are given,Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-45% completed ,316 nos FHTCs are given,Total Pipe laid till date- 10000 m - Work in progress | Kollam WS Sn 2 - AE | |
| 01 Mar 2024 | Package-I-16 % completed, 58 nos FHTCs are given,Total Pipe laid till date-2300m (FHTCS and pipe laying in progress . Package-II-33% completed ,680 FHTCs are given,Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-44% completed ,308 nos FHTCs are given,Total Pipe laid till date- 9870 m - Work in progress | Kollam WS Sn 2 - AE | |
| 26 Feb 2024 | Package-I-15 % completed ,15 % completed ,55 nos FHTCs are given,Total Pipe laid till date-2300m (FHTCS and pipe laying in progress . Package-II-32% completed ,640 FHTCs are given,Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-44% completed ,308 nos FHTCs are given,Total Pipe laid till date- 9870 m - Work in progress | Kollam WS Sn 2 - AE |