| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 Sep 2024 | Package-I-36 % completed, 360 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-III-77 % completed , 2936 FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ) -- Package-II-71 % completed ,1054 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed. | Kollam WS Sn 2 - AE | |
| 26 Sep 2024 | Package-I-36 % completed, 360 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-III-77 % completed , 2936 FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ) -- Package-II-71 % completed ,1054 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed. | Kollam WS Sn 2 - AE | |
| 23 Sep 2024 | Package-I-35 % completed, 350 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-III-77 % completed , 2996 FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ) -- Package-II-71 % completed ,1054 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed. | Kollam WS Sn 2 - AE | |
| 23 Sep 2024 | Package-I-35 % completed, 350 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-II-77 % completed , 2996 FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ) -- Package-III-71 % completed ,1054 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed. | Kollam WS Sn 2 - AE | |
| 18 Sep 2024 | Package-I-35 % completed, 350 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-II-77 % completed , 2996 FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ) -- Package-III-71 % completed ,1054 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed | Kollam WS Sn 2 - AE | |
| 13 Sep 2024 | Package-I-35 % completed, 350 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-II-77 % completed , 2996 FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ) -- Package-III-71 % completed ,1054 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed | Kollam WS Sn 2 - AE | |
| 09 Sep 2024 | Package-I-35 % completed, 350 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-II-77 % completed , 2896 FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ) -- Package-III-71 % completed ,1054 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed | Kollam WS Sn 2 - AE | |
| 05 Sep 2024 | Package-I-35 % completed, 350 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-II-77 % completed , 2896 FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ) -- Package-III-69 % completed ,985 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed, Heavy rain affects progress of work | Kollam WS Sn 2 - AE | |
| 02 Sep 2024 | Package-I-35 % completed, 350 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-II-77 % completed , 2896 FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ) -- Package-III-69 % completed ,985 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed, Heavy rain affects progress of work) | Kollam WS Sn 2 - AE | |
| 29 Aug 2024 | Package-I-34 % completed, 327 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-II-77 % completed , 2853 FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ) -- Package-III-69 % completed ,985 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed, Heavy rain affects progress of work) | Kollam WS Sn 2 - AE |