Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 May 2024 Package-I-26 % completed, 178 nos FHTCs are given,Total Pipe laid till date-3520 m (FHTCS and pipe laying in progress . Package-II-47 % completed , 1350 FHTCs are given, Total Pipe laid till date-8231m(FHTCS and pipe laying in progress ) -- Package-III-63 % completed , 670 nos FHTCs are given, Total Pipe laid till date- 12000 m -Restoration of road by laying concrete concrete under progress. Kollam WS Sn 2 - AE
04 May 2024 Package-I-26 % completed, 165 nos FHTCs are given,Total Pipe laid till date-3520 m (FHTCS and pipe laying in progress . Package-II-46 % completed , 1291 FHTCs are given, Total Pipe laid till date-8231m(FHTCS and pipe laying in progress ) -- Package-III-63 % completed , 629 nos FHTCs are given, Total Pipe laid till date- 12000 m -Restoration of road by laying concrete concrete under progress. Kollam WS Sn 2 - AE
30 Apr 2024 Package-I-26 % completed, 165 nos FHTCs are given,Total Pipe laid till date-3520 m (FHTCS and pipe laying in progress . Package-II-45 % completed , 1291 FHTCs are given, Total Pipe laid till date-8231m(FHTCS and pipe laying in progress ) -- Package-III-62 % completed , 588 nos FHTCs are given, Total Pipe laid till date- 12000 m -Restoration of road by laying concrete concrete under progress. Kollam WS Sn 2 - AE
27 Apr 2024 Package-I-25 % completed, 162 nos FHTCs are given,Total Pipe laid till date-3410m (FHTCS and pipe laying in progress . Package-II-45 % completed , 1291 FHTCs are given, Total Pipe laid till date-8231m(FHTCS and pipe laying in progress ) -- Package-III-61 % completed , 542 nos FHTCs are given, Total Pipe laid till date- 12000 m -Restoration of road by laying concrete concrete under progress. Kollam WS Sn 2 - AE
24 Apr 2024 Package-I-21 % completed, 141 nos FHTCs are given,Total Pipe laid till date-3250m (FHTCS and pipe laying in progress . Package-II-45 % completed , 1291 FHTCs are given, Total Pipe laid till date-8231m(FHTCS and pipe laying in progress ) -- Package-III-60 % completed , 532 nos FHTCs are given, Total Pipe laid till date- 12000 m -Restoration of road by laying concrete concrete under progress. Kollam WS Sn 2 - AE
20 Apr 2024 Package-I-21 % completed, 141 nos FHTCs are given,Total Pipe laid till date-3250m (FHTCS and pipe laying in progress . Package-II-45 % completed , 1213 FHTCs are given, Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-60 % completed , 532 nos FHTCs are given, Total Pipe laid till date- 12000 m - Work in progress Kollam WS Sn 2 - AE
16 Apr 2024 Package-I-20 % completed, 141 nos FHTCs are given,Total Pipe laid till date-3250m (FHTCS and pipe laying in progress . Package-II-43 % completed , 1213 FHTCs are given, Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-59 % completed , 532 nos FHTCs are given, Total Pipe laid till date- 11750 m - Work in progress Kollam WS Sn 2 - AE
12 Apr 2024 Package-I-20 % completed, 141 nos FHTCs are given,Total Pipe laid till date-3250m (FHTCS and pipe laying in progress . Package-II-42 % completed , 1183 FHTCs are given, Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-58 % completed , 532 nos FHTCs are given, Total Pipe laid till date- 11550 m - Work in progress Kollam WS Sn 2 - AE
09 Apr 2024 Package-I-20 % completed, 141 nos FHTCs are given,Total Pipe laid till date-3250m (FHTCS and pipe laying in progress . Package-II-42 % completed , 1183 FHTCs are given, Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-58 % completed , 527 nos FHTCs are given, Total Pipe laid till date- 11550 m - Work in progress Kollam WS Sn 2 - AE
05 Apr 2024 Package-I-20 % completed, 117 nos FHTCs are given,Total Pipe laid till date-3000m (FHTCS and pipe laying in progress . Package-II-41 % completed , 1153 FHTCs are given, Total Pipe laid till date-7792m(FHTCS and pipe laying in progress ) -- Package-III-55 % completed ,471 nos FHTCs are given, Total Pipe laid till date- 11350 m - Work in progress Kollam WS Sn 2 - AE