| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 Jan 2025 | Package-1- Old Muncipal area in Kollam corporation - 45 % completed, 648 nos FHTCs are given,Total Pipe laid till date-6737m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 73 % completed ,1153 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. RE passed . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 92 % completed , 3880nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) | Kollam WS Sn 2 - AE | |
| 28 Jan 2025 | Package-1- Old Muncipal area in Kollam corporation - 45 % completed, 648 nos FHTCs are given,Total Pipe laid till date-6737m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 73 % completed ,1153 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 92 % completed , 3880nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) | Kollam WS Sn 2 - AE | |
| 24 Jan 2025 | Package-1- Old Muncipal area in Kollam corporation - 45 % completed, 648 nos FHTCs are given,Total Pipe laid till date-6737m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 73 % completed ,1153 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 92 % completed , 3845nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) | Kollam WS Sn 2 - AE | |
| 20 Jan 2025 | Package-2- Old Muncipal area in Kollam corporation - 46 % completed, 648 nos FHTCs are given,Total Pipe laid till date-6737m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 73 % completed ,1153 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 87 % completed , 3650nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) | Kollam WS Sn 2 - AE | |
| 14 Jan 2025 | Package-1- Old Muncipal area in Kollam corporation - 45 % completed, 648 nos FHTCs are given,Total Pipe laid till date-6336m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 73 % completed ,1152 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 87 % completed , 3650nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) | Kollam WS Sn 2 - AE | |
| 13 Jan 2025 | Package-1- Old Muncipal area in Kollam corporation - 45 % completed, 648 nos FHTCs are given,Total Pipe laid till date-6336m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1124 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 87 % completed , 3623nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) | Kollam WS Sn 2 - AE | |
| 06 Jan 2025 | Package-1- Old Muncipal area in Kollam corporation - 45 % completed, 648 nos FHTCs are given,Total Pipe laid till date-6336m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1124 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 87 % completed , 3614nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) | Kollam WS Sn 2 - AE | |
| 01 Jan 2025 | Package-1- Old Muncipal area in Kollam corporation - 45 % completed, 648 nos FHTCs are given,Total Pipe laid till date-6336m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1124 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 87 % completed , 3611nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) | Kollam WS Sn 2 - AE | |
| 26 Dec 2024 | Package-1-Old Muncipal area in Kollam corporation - 44 % completed, 614 nos FHTCs are given,Total Pipe laid till date-6045.6 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1124 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 87 % completed , 3574nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) | Kollam WS Sn 2 - AE | |
| 21 Dec 2024 | Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 567 nos FHTCs are given,Total Pipe laid till date-6045.6 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 86 % completed , 3574nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) | Kollam WS Sn 2 - AE |