Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 Jan 2025 Package-1- Old Muncipal area in Kollam corporation - 45 % completed, 648 nos FHTCs are given,Total Pipe laid till date-6737m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 73 % completed ,1153 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. RE passed . Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 92 % completed , 3880nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) Kollam WS Sn 2 - AE
28 Jan 2025 Package-1- Old Muncipal area in Kollam corporation - 45 % completed, 648 nos FHTCs are given,Total Pipe laid till date-6737m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 73 % completed ,1153 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 92 % completed , 3880nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) Kollam WS Sn 2 - AE
24 Jan 2025 Package-1- Old Muncipal area in Kollam corporation - 45 % completed, 648 nos FHTCs are given,Total Pipe laid till date-6737m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 73 % completed ,1153 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 92 % completed , 3845nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) Kollam WS Sn 2 - AE
20 Jan 2025 Package-2- Old Muncipal area in Kollam corporation - 46 % completed, 648 nos FHTCs are given,Total Pipe laid till date-6737m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 73 % completed ,1153 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 87 % completed , 3650nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) Kollam WS Sn 2 - AE
14 Jan 2025 Package-1- Old Muncipal area in Kollam corporation - 45 % completed, 648 nos FHTCs are given,Total Pipe laid till date-6336m (Work in progress). Package-3- Sakthikulangara & Thrikkadavoor zone - 73 % completed ,1152 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-2 -Vadakkevila- Eravipuram & Kilikolloor zone - 87 % completed , 3650nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) Kollam WS Sn 2 - AE
13 Jan 2025 Package-1- Old Muncipal area in Kollam corporation - 45 % completed, 648 nos FHTCs are given,Total Pipe laid till date-6336m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1124 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 87 % completed , 3623nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) Kollam WS Sn 2 - AE
06 Jan 2025 Package-1- Old Muncipal area in Kollam corporation - 45 % completed, 648 nos FHTCs are given,Total Pipe laid till date-6336m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1124 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 87 % completed , 3614nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) Kollam WS Sn 2 - AE
01 Jan 2025 Package-1- Old Muncipal area in Kollam corporation - 45 % completed, 648 nos FHTCs are given,Total Pipe laid till date-6336m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1124 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 87 % completed , 3611nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) Kollam WS Sn 2 - AE
26 Dec 2024 Package-1-Old Muncipal area in Kollam corporation - 44 % completed, 614 nos FHTCs are given,Total Pipe laid till date-6045.6 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1124 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 87 % completed , 3574nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) Kollam WS Sn 2 - AE
21 Dec 2024 Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 567 nos FHTCs are given,Total Pipe laid till date-6045.6 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 86 % completed , 3574nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) Kollam WS Sn 2 - AE