| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 27 Feb 2022 | Pack 1.All components completed except some minor finishing work. Pack 2.Work re started.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed.At Memala sump ,Base slab and haunge concreted. Pack 4.Re-tendered.Package-V-Work order issued. Over all progress 53%, Bill for 75% of the completed project submitted,balance bill under preparation | Koothuparamba Proj AE 2 | |
| 24 Feb 2022 | Pack 1.Intake Well cum pumphouse,electrical room,retaining wall and all connected works completed.11 MLD WTP- completed. .Compound wall work in progress.Raw water pumping main completed.Some finishing work in progress. Pack 2.Work re started.But no progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed.At Memala sump ,Base slab and haunge concreted. Pack 4.Estimate recalculated and submitted .Package-V-Work order issued. Over all progress 50%, Bill for 75% of the completed project submitted,balance bill under preparation | Koothuparamba Proj AE 2 | |
| 21 Feb 2022 | Pack 1.intake Well cum pumphouse,electrical room,retaining wall and all connected works completed.11 MLD WTP- completed. .Compound wall work in progress.Raw water pumping main completed.Some finishing work in progress. Pack 2.Work re started.But no progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed.At Memala sump ,Base slab concreted. Pack 4.Estimate recalculated and submitted .Package-V-Work order issued. Over all progress 50%, Bill for 75% of the completed project submitted,balance bill under preparation | Koothuparamba Proj AE 2 | |
| 17 Feb 2022 | Pack 1.intake Well cum pumphouse,electrical room,retaining wall and all connected works completed.11 MLD WTP- completed. .Compound wall work in progress.Raw water pumping main completed.Some finishing work in progress. Pack 2.Work re started.But no progress. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work is almost completed.At Memala sump ,Base slab concreted. Pack 4.Estimate recalculated and submitted .Package-V-Work order issued. Over all progress 50%, Bill for 75% of the completed project submitted,balance bill under preparation | Koothuparamba Proj AE 2 | |
| 14 Feb 2022 | Pack 1.intake Well cum pumphouse,electrical room,retaining wall and all connected works completed.11 MLD WTP- completed. .Compound wall work in progress.Raw water pumping main completed.Some finishing work in progress. Pack 2.Work re started.But no progress. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work is almost completed.At Memala sump ,Base slab concreted. Pack 4.Estimate recalculated and submitted .Package-V-Work order issued. Over all progress 50%, Bill for 75% of the completed project submitted,balance bill under preparation | Koothuparamba Proj AE 2 | |
| 14 Feb 2022 | Intake Well cum pumphouse,electrical room,retaining wall and all connected works completed.11 MLD WTP-almost completed. .Compound wall work in progress.Raw water pumping main almost completed. | Koothuparamba Proj AE 2 | |
| 11 Feb 2022 | Pack 1.intake Well cum pumphouse,electrical room,retaining wall and all connected works completed.11 MLD WTP-almost completed. .Compound wall work in progress.Raw water pumping main almost completed. Pack 2.Work re started.But no progress. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work in almost completed.At Memala sump ,Base slab concreted. Pack 4.Estimate recalculated and submitted .Package-V-Work order issued. 2 offers received. Over all progress 50%, Bill for 75% of the completed project submitted,balance bill under preparation | Koothuparamba Proj AE 2 | |
| 07 Feb 2022 | Pack 1.intake Well cum pumphouse,electrical room,retaining wall and all connected works completed.11 MLD WTP-almost completed. .Compound wall work in progress.Raw water pumping main almost completed. Pack 2.Work re started.But no progress. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work in almost completed.At Memala sump ,Base slab concreted. Pack 4.Estimate recalculated and submitted .Package-V-Tendered. 2 offers received. Over all progress 50%, Bill for 75% of the completed project submitted,balance bill under preparation | Koothuparamba Proj AE 2 | |
| 06 Feb 2022 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. Retaining wall completed. Electrical room completed.Pump house completed. WTP-Clarifoculator completed.Filter completed.Wash water tank completed.Clear water tank completed . Raw water pipe line work completed . Aerator work completed.Compound wall work in progress. Pack 2.Work re started.But no progress. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work in almost completed.At Memala sump ,Base slab concreted. Pack 4.Estimate recalculated and submitted .Package-V-Tendered. 2 offers received. Over all progress 45%, Bill for 75% of the completed project submitted,balance bill under preparation | Koothuparamba Proj AE 2 | |
| 04 Feb 2022 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. Retaining wall completed. Electrical room completed.Pump house completed. WTP-Clarifoculator completed.Filter completed.Wash water tank completed.Clear water tank completed . Raw water pipe line work completed . Aerator work completed.Compound wall work in progress. Pack 2.Work re started.But no progress. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work in almost completed.Earth work of sump at Memala completed. PCC done.Base slab reinforcement work started. Pack 4.Estimate recalculated and submitted .Package-V-Tendered. 2 offers received. Over all progress 45%, Bill for 75% of the completed project submitted,balance bill under preparation | Koothuparamba Proj AE 2 |