| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 02 Apr 2022 | Pack 1.work completed,final bill submitted . Pack 2.Work re started.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed..At Memala sump Side wall 2nd stage concreted.Pipe laying work started. Pack 4.Re-tendered. Package-V-Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted. | Koothuparamba Proj AE 2 | |
| 30 Mar 2022 | Pack 1.work completed,final bill submitted . Pack 2.Work re started.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed.At Memala sump Side wall 2nd stage concreted.Pack 4.Re-tendered.Package-V-Work order issued. Agreement executed.Over all progress 50%, Bill for 100% of the completed project (Package I)submitted. | Koothuparamba Proj AE 2 | |
| 24 Mar 2022 | Pack 1.work completed,final bill submitted . Pack 2.Work re started.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed.At Memala sump Side wall 2nd stage concreted.Pack 4.Re-tendered.Package-V-Work order issued. Agreement executed.Over all progress 50%, Bill for 100% of the completed project (Package I)submitted. | Koothuparamba Proj AE 2 | |
| 21 Mar 2022 | Pack 1.work completed,final bill submitted . Pack 2.Work re started.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed.At Memala sump Side wall first stage concreted.Pack 4.Re-tendered.Package-V-Work order issued. Agreement executed.Over all progress 50%, Bill for 100% of the completed project (Package I)submitted. | Koothuparamba Proj AE 2 | |
| 17 Mar 2022 | Pack 1.work completed,final bill submitted . Pack 2.Work re started.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed.At Memala sump Side wall first stage concreted.Pack 4.Re-tendered.Package-V-Work order issued. Agreement executed.Over all progress 50%, Bill for 100% of the completed project (Package I)submitted. | Koothuparamba Proj AE 2 | |
| 14 Mar 2022 | Pack 1.work completed,final bill submitted . Pack 2.Work re started.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed.At Memala sump Side wall first stage concreted.Pack 4.Re-tendered.Package-V-Work order issued. Agreement executed.Over all progress 50%, Bill for 100% of the completed project (Package I)submitted. | Koothuparamba Proj AE 2 | |
| 10 Mar 2022 | Pack 1.work completed,final bill submitted . Pack 2.Work re started.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed.At Memala sump ,Base slab and haunge concreted. Side wall first stage concreted.Pack 4.Re-tendered.Package-V-Work order issued. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted. | Koothuparamba Proj AE 2 | |
| 07 Mar 2022 | Pack 1.work completed,final bill submitted . Pack 2.Work re started.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed.At Memala sump ,Base slab and haunge concreted. Side wall first stage concreted.Pack 4.Re-tendered.Package-V-Work order issued. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted. | Koothuparamba Proj AE 2 | |
| 06 Mar 2022 | Pack 1.work completed,final bill submitted . Pack 2.Work re started.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed.At Memala sump ,Base slab and haunge concreted. Side wall first stage concreted.Pack 4.Re-tendered.Package-V-Work order issued. Over all progress 53%, Bill for 100% of the completed project (Package I)submitted. | Koothuparamba Proj AE 2 | |
| 02 Mar 2022 | Pack 1.All components completed . Pack 2.Work re started.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed.At Memala sump ,Base slab and haunge concreted. Pack 4.Re-tendered.Package-V-Work order issued. Over all progress 53%, Bill for 100% of the completed project (Package I)submitted. | Koothuparamba Proj AE 2 |