Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 May 2022 Pack 1.work completed,final bill submitted . Pack 2.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed..At Memala sump Side wall 3rd stage concreted.Cover slab concrete completed.Pump house work in progress.Pipe laying work in progress. Pack 4.Re-tendered. Package-V-Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted Koothuparamba Proj AE 2
05 May 2022 Pack 1.work completed,final bill submitted . Pack 2.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed..At Memala sump Side wall 3rd stage concreted.Cover slab work in progress.Pipe laying work in progress. Pack 4.Re-tendered. Package-V-Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted. Koothuparamba Proj AE 2
03 May 2022 Pack 1.work completed,final bill submitted . Pack 2.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed..At Memala sump Side wall 3rd stage concreted.Cover slab work in progress.Pipe laying work in progress. Pack 4.Re-tendered. Package-V-Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted. Koothuparamba Proj AE 2
28 Apr 2022 Pack 1.work completed,final bill submitted . Pack 2.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed..At Memala sump Side wall 3rd stage concreted.Cover slab work in progress.Pipe laying work in progress. Pack 4.Re-tendered. Package-V-Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted. Koothuparamba Proj AE 2
25 Apr 2022 Pack 1.work completed,final bill submitted . Pack 2.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed..At Memala sump Side wall 3rd stage concreted.Cover slab work in progress.Pipe laying work in progress. Pack 4.Re-tendered. Package-V-Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted. Koothuparamba Proj AE 2
21 Apr 2022 Pack 1.work completed,final bill submitted . Pack 2.Work re started.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed..At Memala sump Side wall 3rd stage concreted.Pipe laying work started. Pack 4.Re-tendered. Package-V-Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted. Koothuparamba Proj AE 2
17 Apr 2022 Pack 1.work completed,final bill submitted . Pack 2.Work re started.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed..At Memala sump Side wall 3rd stage concreted.Pipe laying work started. Pack 4.Re-tendered. Package-V-Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted. Koothuparamba Proj AE 2
12 Apr 2022 Pack 1.work completed,final bill submitted . Pack 2.Work re started.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed..At Memala sump Side wall 3rd stage concreted.Pipe laying work started. Pack 4.Re-tendered. Package-V-Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted. Koothuparamba Proj AE 2
07 Apr 2022 Pack 1.work completed,final bill submitted . Pack 2.Work re started.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed..At Memala sump Side wall 2nd stage concreted.Pipe laying work started. Pack 4.Re-tendered. Package-V-Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted. Koothuparamba Proj AE 2
04 Apr 2022 Pack 1.work completed,final bill submitted . Pack 2.Work re started.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed..At Memala sump Side wall 2nd stage concreted.Pipe laying work started. Pack 4.Re-tendered. Package-V-Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted. Koothuparamba Proj AE 2