Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Aug 2022 Pack 1.work completed, final bill submitted. Pack 2.Pipe laying work almost completed, Steel bridge work couldn’t start due to heavy rain. Pack 3.Pump house work of sump at Kambipalam completed. Finishing work is almost completed. At Memala sump Cover slab concrete completed. Pump house Roof slab concrete postponed due to heavy rain. Pumping main work restarted. Pack 4. Estimate split up and re tendered and work order issued. Package-V- Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed Koothuparamba Proj AE 2
01 Aug 2022 Pack 1.work completed, final bill submitted. Pack 2.Pipe laying work almost completed, Steel bridge work couldn’t start due to heavy rain. Pack 3.Pump house work of sump at Kambipalam completed. Finishing work is almost completed. At Memala sump Cover slab concrete completed. Pump house Roof slab concrete postponed due to heavy rain. Pumping main work restarted. Pack 4. Estimate split up and re tendered offer received and submitted to CE for approval. Package-V- Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed. Koothuparamba Proj AE 2
26 Jul 2022 Pack 1.work completed, final bill submitted. Pack 2.Pipe laying work almost completed, Steel bridge work couldn’t start due to heavy rain. Pack 3.Pump house work of sump at Kambipalam completed. Finishing work is almost completed. At Memala sump Cover slab concrete completed. Pump house Roof slab concrete scheduled on 30.07.2022. Pumping main work restarted. Pack 4. Estimate split up and re tendered offer received and under scrutiny. Package-V- Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed. Koothuparamba Proj AE 2
24 Jun 2022 Pack 1.work completed,final bill submitted . Pack 2.Pipe laying work almost completed.work stopped during the periode of Vyshakha Mahotsavam at Kottiyuras per the order of Dist.collector Kannur. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed..At Memala sump Cover slab concrete completed.Pump house work in progress.Pipe laying work stopped during the periode of Vyshakha Mahotsavam at Kottiyuras per the order of Dist.collector Kannur . Pack 4.Re-tendered. Package-V-Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted Koothuparamba Proj AE 2
09 Jun 2022 Pack 1.work completed,final bill submitted . Pack 2.Pipe laying work almost completed.work stopped during the periode of Vyshakha Mahotsavam at Kottiyuras per the order of Dist.collector Kannur. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed..At Memala sump Cover slab concrete completed.Pump house work in progress.Pipe laying work stopped during the periode of Vyshakha Mahotsavam at Kottiyuras per the order of Dist.collector Kannur . Pack 4.Re-tendered. Package-V-Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted Koothuparamba Proj AE 2
03 Jun 2022 Pack 1.work completed,final bill submitted . Pack 2.Pipe laying work almost completed.work stopped during the periode of Vyshakha Mahotsavam at Kottiyuras per the order of Dist.collector Kannur. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed..At Memala sump Side wall 3rd stage concreted.Cover slab concrete completed.Pump house work in progress.Pipe laying work stopped during the periode of Vyshakha Mahotsavam at Kottiyuras per the order of Dist.collector Kannur . Pack 4.Re-tendered. Package-V-Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted Koothuparamba Proj AE 2
29 May 2022 Pack 1.work completed,final bill submitted . Pack 2.Pipe laying work almost completed.work stopped during the periode of Vyshakha Mahotsavam at Kottiyuras per the order of Dist.collector Kannur. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed..At Memala sump Side wall 3rd stage concreted.Cover slab concrete completed.Pump house work in progress.Pipe laying work stopped during the periode of Vyshakha Mahotsavam at Kottiyuras per the order of Dist.collector Kannur . Pack 4.Re-tendered. Package-V-Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted Koothuparamba Proj AE 2
26 May 2022 Pack 1.work completed,final bill submitted . Pack 2.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed..At Memala sump Side wall 3rd stage concreted.Cover slab concrete completed.Pump house work in progress.Pipe laying work stopped during the periode of Vyshakha Mahotsavam at Kottiyuras per the order of Dist.collector Kannur . Pack 4.Re-tendered. Package-V-Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted Koothuparamba Proj AE 2
23 May 2022 Pack 1.work completed,final bill submitted . Pack 2.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed..At Memala sump Side wall 3rd stage concreted.Cover slab concrete completed.Pump house work in progress.Pipe laying work stopped during the periode of Vyshakha Mahotsavam at Kottiyuras per the order of Dist.collector Kannur . Pack 4.Re-tendered. Package-V-Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted Koothuparamba Proj AE 2
18 May 2022 Pack 1.work completed,final bill submitted . Pack 2.Pipe laying in progress. Pack 3.Pump house work of sump at Kambipalam completed.Finishing work is almost completed..At Memala sump Side wall 3rd stage concreted.Cover slab concrete completed.Pump house work in progress.Pipe laying work stopped during the periode of Vyshakha Mahotsavam at Kottiyuras per the order of Dist.collector Kannur . Pack 4.Re-tendered. Package-V-Work order issued. Agreement executed. Over all progress 50%, Bill for 100% of the completed project (Package I)submitted Koothuparamba Proj AE 2