Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Nov 2022 Pack 1.work completed, final bill submitted. Pack 2.Pipe laying work almost completed, Steel bridge work couldn’t start due to heavy rain. Pack 3.Pump house work of sump at Kambipalam completed. Finishing work is almost completed. At Memala sump Cover slab concrete completed. Pump house Roof slab concrete completed plastering work started. Pumping main 4650 m laid. Pack 4. part I Sump site at Manjalampuram and Poovathinchola earth work excavation completed and manjalampuram sump pcc completed and bsase slab of sump reinforcement work started . Pack 4 part II Tank site Vellunni excavation started and 300 mm and 200 mm DI K9 pipe supplied and 800 m DI pipe laid and first and part bill submitted. Package-V- Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed Koothuparamba Proj AE 2
27 Oct 2022 Pack 1.work completed, final bill submitted. Pack 2.Pipe laying work almost completed, Steel bridge work couldn’t start due to heavy rain. Pack 3.Pump house work of sump at Kambipalam completed. Finishing work is almost completed. At Memala sump Cover slab concrete completed. Pump house Roof slab concrete completed plastering work started. Pumping main 4650 m laid. Pack 4. part I Sump site at Manjalampuram and Poovathinchola earth work excavation completed and manjalampuram sump pcc completed and bsase slab of sump work started . Pack 4 part II Tank site Vellunni excavation started and 300 mm and 200 mm DI K9 pipe supplied and 700 m DI pipe laid and first and part bill submitted. Package-V- Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed Koothuparamba Proj AE 2
21 Oct 2022 Pack 1.work completed, final bill submitted. Pack 2.Pipe laying work almost completed, Steel bridge work couldn’t start due to heavy rain. Pack 3.Pump house work of sump at Kambipalam completed. Finishing work is almost completed. At Memala sump Cover slab concrete completed. Pump house Roof slab concrete completed plastering work started. Pumping main 4650 m laid. Pack 4. part I Sump site at Manjalampuram and Poovathinchola earth work excavation completed and manjalampuram sump pcc completed and bsase slab of sump work started . Pack 4 part II Tank site Vellunni excavation started and 300 mm and 200 mm DI K9 pipe supplied and 600 m DI pipe laid and first and part bill submitted. Package-V- Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed Koothuparamba Proj AE 2
17 Oct 2022 Pack 1.work completed, final bill submitted. Pack 2.Pipe laying work almost completed, Steel bridge work couldn’t start due to heavy rain. Pack 3.Pump house work of sump at Kambipalam completed. Finishing work is almost completed. At Memala sump Cover slab concrete completed. Pump house Roof slab concrete completed plastering work started. Pumping main 4650 m laid. Pack 4. part I Sump site at Manjalampuram and Poovathinchola earth work excavation completed and manjalampuram sump pcc completed . Pack 4 part II Tank site Vellunni excavation started and 300 mm and 200 mm DI K9 pipe supplied and 500 m DI pipe laid. Package-V- Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed Koothuparamba Proj AE 2
06 Oct 2022 Pack 1.work completed, final bill submitted. Pack 2.Pipe laying work almost completed, Steel bridge work couldn’t start due to heavy rain. Pack 3.Pump house work of sump at Kambipalam completed. Finishing work is almost completed. At Memala sump Cover slab concrete completed. Pump house Roof slab concrete completed plastering work started. Pumping main 4650 m laid. Pack 4. part I Sump site at Manjalampuram and Poovathinchola earth work excavation completed. Pack 4 part II Tank site Vellunni excavation started and 300 mm and 200 mm DI K9 pipe supplied . Package-V- Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed Koothuparamba Proj AE 2
12 Sep 2022 Pack 1.work completed, final bill submitted. Pack 2.Pipe laying work almost completed, Steel bridge work couldn’t start due to heavy rain. Pack 3.Pump house work of sump at Kambipalam completed. Finishing work is almost completed. At Memala sump Cover slab concrete completed. Pump house Roof slab concrete completed. Pumping main work restarted. Pack 4. The work dropped and rearranged as part I and part II and work order issued and work started. Package-V- Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed Koothuparamba Proj AE 2
03 Sep 2022 Pack 1.work completed, final bill submitted. Pack 2.Pipe laying work almost completed, Steel bridge work couldn’t start due to heavy rain. Pack 3.Pump house work of sump at Kambipalam completed. Finishing work is almost completed. At Memala sump Cover slab concrete completed. Pump house Roof slab concrete completed. Pumping main work restarted. Pack 4. The work dropped and rearranged as part I and part II and work order issued. Package-V- Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed Koothuparamba Proj AE 2
30 Aug 2022 Pack 1.work completed, final bill submitted. Pack 2.Pipe laying work almost completed, Steel bridge work couldn’t start due to heavy rain. Pack 3.Pump house work of sump at Kambipalam completed. Finishing work is almost completed. At Memala sump Cover slab concrete completed. Pump house Roof slab concrete completed. Pumping main work restarted. Pack 4. The work dropped and rearranged as part I and part II and work order issued. Package-V- Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed Koothuparamba Proj AE 2
25 Aug 2022 Pack 1.work completed, final bill submitted. Pack 2.Pipe laying work almost completed, Steel bridge work couldn’t start due to heavy rain. Pack 3.Pump house work of sump at Kambipalam completed. Finishing work is almost completed. At Memala sump Cover slab concrete completed. Pump house Roof slab concrete completed. Pumping main work stopped due to heavy rain. Pack 4. Estimate split up and re tendered and work order issued. Package-V- Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed Koothuparamba Proj AE 2
16 Aug 2022 Pack 1.work completed, final bill submitted. Pack 2.Pipe laying work almost completed, Steel bridge work couldn’t start due to heavy rain. Pack 3.Pump house work of sump at Kambipalam completed. Finishing work is almost completed. At Memala sump Cover slab concrete completed. Pump house Roof slab concrete completed. Pumping main work restarted. Pack 4. Estimate split up and re tendered and work order issued. Package-V- Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed Koothuparamba Proj AE 2