Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Jan 2023 Pack 1- work completed, final bill submitted. Pack 2- foundation trench for Steel bridge started,350mm Di pipe 4250m completed. Pack III - out of 8.83km pipeline 7.4km supplied and 4.617km pipe laid. work progress is slow.Notice issued several times to the Contractor Udayapuram Labour contractor Society. Pack 4 (part -I) -, Manjalampuram sump completed pumphouse column work started and Poovathinchola sump side wall upto 2m level concrete work in progress. Pack 4 part II 300 mm DI pipe 2000m laid and 200 mm DI pipe 950m laid,work in progress.. Package-V -Internal wiring of pump houses , electrical room and earthing work completed, pumpset not supplied Koothuparamba Proj AE 2
10 Jan 2023 Pack 1- work completed, final bill submitted. Pack 2- foundation trench for Steel bridge started,350mm Di pipe 4250m laid. Pack III - out of 8.83km pipeline 7.4km supplied and 4.617km pipe laid. Pack 4 (part -I) -, Manjalampuram sump completed pumphouse column work started and Poovathinchola sump side wall upto 2m level on progress. Pack 4 part II 300 mm DI pipe 2000m laid and 200 mm DI pipe 950m laid. Package-V -Internal wiring of pump houses and electrical room completed,pumpset not supplied Koothuparamba Proj AE 2
10 Jan 2023 Pack 1- work completed, final bill submitted. Pack 2- foundation trench for Steel bridge started,350mm Di pipe 4450m laid. Pack III - Pipeline work in progress. Pack 4 (part -I) -, Manjalampuram sump pumphouse column work started and Poovathinchola sump side wall upto 2m level on progress.Pack 4 part II 300 mm DI pipe 1600m laid and 200 mm DI pipe 920m laid. Package-V -Internal wiring of pump houses and electrical room completed Koothuparamba Proj AE 2
28 Dec 2022 Pack 1- work completed, final bill submitted. Pack 2- 6nos of valave chamber completed .Pack III - 200 mm DI pipe laying work restarted . Pack 4 (part -I) -, Manjalampuram cover slab and Poovathinchola base slab concrete complete 4 part II 300 mm DI pipe 1600m laid and 200 mm DI pipe 900 m laid. Package-V -earthing completed Koothuparamba Proj AE 2
17 Dec 2022 Pack 1- work completed, final bill submitted. Pack 2- Work restarted on 15-12-2022.Pack III - 200 mm DI pipe of 1083.5 ma supplied agianst the balance quantity of 1994 m. Pack 4 (part -I) -, Manjalampuram sump reinforcement work is completed and Poovathinchola sump reinforcement work in progressPack 4 part II 300 mm DI pipe 1600m laid and 200 mm DI pipe 850m laid. Package-V -Internal wiring of pump houses and electrical room completed Koothuparamba Proj AE 2
08 Dec 2022 Pack 1- work completed, final bill submitted. Pack 2- Pipe laying work almost completed, Steel bridge work couldn’t start due to site adverse site condition. Pack 3 - Pump house work of sump at Kambipalam and Memal completed, finishing work pending. Pipe laying work restarted. Pack 4 (part -I) -, Manjalampuram Sump reinforcement work for covers lab is in progress Poovanthinchola sump reinforcement for base slab is started.Pack 4 part II Sump at Vellunni earth work excavation completed and 300 mm DI pipe 1100 m and 200 mm DI pipe 500 m laid. Package-V- Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed Koothuparamba Proj AE 2
30 Nov 2022 Pack 1- work completed, final bill submitted. Pack 2- Pipe laying work almost completed, Steel bridge work couldn’t start due to site adverse site condition. Pack 3 - Pump house work of sump at Kambipalam and Memal completed, finishing work pending. Pumping main 4650 m laid.200mm DI pipe of 545m supplied against the balance quantity of 1800m. Pack 4 (part -I) -Cover slab of sump at Manjalampuram started and pcc of Poovathinchola sump completed.Pack 4 part II Sump at Vellunni earth work excavation completed and 300 mm DI pipe 1100 m and 200 mm DI pipe 500 m laid. Package-V- Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed Koothuparamba Proj AE 2
19 Nov 2022 Pack 1- work completed, final bill submitted. Pack 2- Pipe laying work almost completed, Steel bridge work couldn’t start due to site adverse site condition. Pack 3 - Pump house work of sump at Kambipalam and Memal completed, finishing work pending. Pumping main 4650 m laid.200mm DI pipe of 545m supplied against the balance quantity of 1800m. Pack 4 (part -I) - Sump work at Manjalampuram wall up to 1m completed and Poovathinchola earth work excavation completed. Manjalampuram sump 3metre side wall concrete completed.Pack 4 part II Tank site Vellunni excavation completed and 300 mm and 200 mm DI K9 pipe supplied and 900 m DI pipe laid and first and part bill submitted. Package-V- Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed Koothuparamba Proj AE 2
19 Nov 2022 Pack 1- work completed, final bill submitted. Pack 2- Pipe laying work almost completed, Steel bridge work couldn’t start due to site adverse site condition. Pack 3 - Pump house work of sump at Kambipalam and Memal completed, finishing work pending. Pumping main 4650 m laid. 200mm DI pipe 845m supplied.Pack 4 (part -I) - Sump work at Manjalampuram wall up to 1m completed and Poovathinchola earth work excavation completed. sump work at Manjalampuram 3m side wall concrete completed.Pack 4 part II Tank site Vellunni excavation completed and 300 mm and 200 mm DI K9 pipe supplied and 900 m DI pipe laid and first and part bill submitted. Package-V- Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed Koothuparamba Proj AE 2
14 Nov 2022 Pack 1- work completed, final bill submitted. Pack 2- Pipe laying work almost completed, Steel bridge work couldn’t start due to site adverse site condition. Pack 3 - Pump house work of sump at Kambipalam and Memal completed, finishing work pending. Pumping main 4650 m laid. Pack 4 (part -I) - Sump work at Manjalampuram wall up to 1m completed and Poovathinchola earth work excavation completed. Pack 4 part II Tank site Vellunni excavation completed and 300 mm and 200 mm DI K9 pipe supplied and 900 m DI pipe laid and first and part bill submitted. Package-V- Electrical drawings submitted to electrical inspectorate for approval Manufacturing pump set and transformers completed Koothuparamba Proj AE 2