| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 15 Feb 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge abutment work completed.Valve chamber work completed.Pack III - out of 8.83km pipeline 7.4km supplied and 4.617km pipe laid. work progress is slow.Notice issued several times to the Contractor Udayapuram Labour contractor Society. Pipe laying work at Culvert ongoing.slow progress.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola column work started. Manjalampuram sump inside plastering completed and outside plastering on progress.Pack 4 part II pipe laying work in progress.GL tank at Velooni base slab concrete completed. Package-V -Earthing at Substation yard completed as per the direction of electrical inspectorate,Pumpset and transformer supplied on site ,Erection of transformer and pump sets are in progress | Koothuparamba Proj AE 2 | |
| 10 Feb 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge abutment work completed.Pack III - out of 8.83km pipeline 7.4km supplied and 4.617km pipe laid. work progress is slow.Notice issued several times to the Contractor Udayapuram Labour contractor Society. Pipe laying work at Culvert ongoing.slow progress.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola column work started. Pack 4 part II pipe laying work in progress.GL tank at Velooni base slab reinforcement work in progress.. Package-V -Earthing at Substation yard completed as per the direction of electrical inspectorate,Pumpset and transformer supplied on site ,work on progress | Koothuparamba Proj AE 2 | |
| 08 Feb 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge abutment work completed.Pack III - out of 8.83km pipeline 7.4km supplied and 4.617km pipe laid. work progress is slow.Notice issued several times to the Contractor Udayapuram Labour contractor Society. Pipe laying work at Culvert ongoing.slow progress.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola column work started. Pack 4 part II pipe laying work in progress.GL tank at Velooni base slab reinforcement work in progress.. Package-V -Earthing at Substation yard completed as per the direction of electrical inspectorate,Pumpset supplied on site work on progress | Koothuparamba Proj AE 2 | |
| 04 Feb 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work abutment work in progress.Pack III - out of 8.83km pipeline 7.4km supplied and 4.617km pipe laid. work progress is slow.Notice issued several times to the Contractor Udayapuram Labour contractor Society. Pipe laying work at Culvert ongoing.Pack 4 (part -I) -, Manjalampuram sump completed pumphouse column work started and Sump at poovathinchola cover slab concrete completed. pumphouse work started.Pack 4 part II pipe laying work in progress.GL tank at Velooni PCC work started.. Package-V -Earthing at Substation yard completed as per the direction of electrical inspectorate,Pumpset supplied on site work on progress | Koothuparamba Proj AE 2 | |
| 01 Feb 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work abutment work in progress.Pack III - out of 8.83km pipeline 7.4km supplied and 4.617km pipe laid. work progress is slow.Notice issued several times to the Contractor Udayapuram Labour contractor Society. Pipe laying work at Culvert ongoing.Pack 4 (part -I) -, Manjalampuram sump completed pumphouse column work started and Sump at poovathinchola cover slab concrete completed. Pack 4 part II pipe laying work in progress. Package-V -Earthing at Substation yard completed as per the direction of electrical inspectorate,Pumpset supplied work on progress | Koothuparamba Proj AE 2 | |
| 25 Jan 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work in progress.Pack III - out of 8.83km pipeline 7.4km supplied and 4.617km pipe laid. work progress is slow.Notice issued several times to the Contractor Udayapuram Labour contractor Society. Pipe laying work at Culvert ongoing.Pack 4 (part -I) -, Manjalampuram sump completed pumphouse column work started and Sump at poovathinchola cover slab formwork on progress. Pack 4 part II pipe laying work in progress. Package-V -Earthing at Substation yard completed as per the direction of electrical inspectorate,Pumpset not supplied | Koothuparamba Proj AE 2 | |
| 23 Jan 2023 | Pack 1- work completed, final bill submitted. Pack 2-foundation work for Steel bridge completed,,350mm Di pipe 4250m completed. Pack III - out of 8.83km pipeline 7.4km supplied and 4.617km pipe laid. work progress is slow.Notice issued several times to the Contractor Udayapuram Labour contractor Society. Pipe laying work at Culvert ongoing.Pack 4 (part -I) -, Manjalampuram sump completed pumphouse column work started and Sump at poovathinchola cover slab formwork started. Pack 4 part II 200 mm DI pipe 1070m laid,work in progress. Package-V -Earthing at Substation yard completed as per the direction of electrical inspectorate,Pumpset not supplied | Koothuparamba Proj AE 2 | |
| 18 Jan 2023 | Pack 1- work completed, final bill submitted. Pack 2-PCC work for Steel bridge completed,350mm Di pipe 4250m completed. Pack III - out of 8.83km pipeline 7.4km supplied and 4.617km pipe laid. work progress is slow.Notice issued several times to the Contractor Udayapuram Labour contractor Society. Pack 4 (part -I) -, Manjalampuram sump completed pumphouse column work started and Poovathinchola sump side wall upto third level concreting on progress. Pack 4 part II 200 mm DI pipe 1070m laid,work in progress. Package-V -Earthing at Substation yard completed as per the direction of electrical inspectorate,Pumpset not supplied | Koothuparamba Proj AE 2 | |
| 13 Jan 2023 | Pack 1- work completed, final bill submitted. Pack 2- foundation trench for Steel bridge started,350mm Di pipe 4250m completed. Pack III - out of 8.83km pipeline 7.4km supplied and 4.617km pipe laid. work progress is slow.Notice issued several times to the Contractor Udayapuram Labour contractor Society. Pack 4 (part -I) -, Manjalampuram sump completed pumphouse column work started and Poovathinchola sump side wall upto 2m level concrete completed. Pack 4 part II 300 mm DI pipe 2000m laid and 200 mm DI pipe 1050m laid,work in progress.. Package-V -Internal wiring of pump houses , electrical room and earthing work completed, pumpset not supplied | Koothuparamba Proj AE 2 | |
| 11 Jan 2023 | Pack 1- work completed, final bill submitted. Pack 2- foundation trench for Steel bridge started,350mm Di pipe 4250m completed. Pack III - out of 8.83km pipeline 7.4km supplied and 4.617km pipe laid. work progress is slow.Notice issued several times to the Contractor Udayapuram Labour contractor Society. Pack 4 (part -I) -, Manjalampuram sump completed pumphouse column work started and Poovathinchola sump side wall upto 2m level concrete work in progress. Pack 4 part II 300 mm DI pipe 2000m laid and 200 mm DI pipe 1050m laid,work in progress.. Package-V -Internal wiring of pump houses , electrical room and earthing work completed, pumpset not supplied | Koothuparamba Proj AE 2 |