| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Apr 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work completeds.Pack III -Pipe laying work slow in progress.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola work on progress.Pack 4 part II 300 mm DI pipe 1960m laid and 200 mm DI pipe 1150m laid,work in progress, GL Tank at Vellooni cover slab concrete completed,pumphouse work started.Package-V -erection of transformer ongoing , termination work ongoing, Pump interconnection work ongoing. | Koothuparamba Proj AE 2 | |
| 30 Mar 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work on progress.Pack III -Pipe laying work on progress.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola work on progress.Pack 4 part II 300 mm DI pipe 1960m laid and 200 mm DI pipe 1150m laid,work in progress, GL Tank at Vellooni cover slab concrete completed.Package-V -Erection of transformer are in progress | Koothuparamba Proj AE 2 | |
| 16 Mar 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work on progress.Pack III -Pipe laying work on progress.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola work on progress.Pack 4 part II 300 mm DI pipe 1960m laid and 200 mm DI pipe 1150m laid,work in progress,GL Tank at Vellooni cover slab concrete completed.Package-V -Erection of transformer are in progress | Koothuparamba Proj AE 2 | |
| 09 Mar 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work on progress.Pack III -Pipe laying work on progress.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola column work started.Pack 4 part II 300 mm DI pipe 1900m laid and 200 mm DI pipe 1150m laid,work in progress,GL Tank at Vellooni side wall third level concrete completed.Package-V -Erection of transformer are in progress | Koothuparamba Proj AE 2 | |
| 02 Mar 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work on progress.Pack III -Pipe laying work on progress.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola column work started.Pack 4 part II 300 mm DI pipe 1900m laid and 200 mm DI pipe 1150m laid,work in progress,GL Tank at Vellooni side wall third level concrete on progress.Package-V -Erection of transformer and pump sets are in progress | Koothuparamba Proj AE 2 | |
| 01 Mar 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work on progress.Pack III -Pipe laying work on progress.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola column work started.Pack 4 part II 300 mm DI pipe 1900m laid and 200 mm DI pipe 1150m laid,work in progress,GL Tank at Vellooni side wall concrete completed upto 1m height.Package-V -Erection of transformer and pump sets are in progress | Koothuparamba Proj AE 2 | |
| 27 Feb 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work on progress.Pack III -Pipe laying work on progress.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola column work started. Manjalampuram sump inside plastering and outside plastering completed.Pack 4 part II 300 mm DI pipe 1900m laid and 200 mm DI pipe 1150m laid,work in progress,GL Tank at Vellooni side wall concrete completed upto 1m height.Package-V -Earthing at Substation yard completed as per the direction of electrical inspectorate,Pumpset and transformer supplied on site ,Erection of transformer and pump sets are in progress | Koothuparamba Proj AE 2 | |
| 23 Feb 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work on progress.Pack III -Pipe laying work on progress.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola column work started. Manjalampuram sump inside plastering and outside plastering completed.Pack 4 part II pipe laying work in progress.GL tank at Velooni side wall concrete on progress. Package-V -Earthing at Substation yard completed as per the direction of electrical inspectorate,Pumpset and transformer supplied on site ,Erection of transformer and pump sets are in progress | Koothuparamba Proj AE 2 | |
| 20 Feb 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge abutment work completed.Valve chamber work completed.Pack III - out of 8.83km pipeline 7.4km supplied and 4.617km pipe laid. work progress is slow.Notice issued several times to the Contractor Udayapuram Labour contractor Society. Pipe laying work at Culvert ongoing.slow progress.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola column work started. Manjalampuram sump inside plastering and outside plastering completed.Pack 4 part II pipe laying work in progress.GL tank at Velooni side wall reinforcement work completed and form work on progress. Package-V -Earthing at Substation yard completed as per the direction of electrical inspectorate,Pumpset and transformer supplied on site ,Erection of transformer and pump sets are in progress | Koothuparamba Proj AE 2 | |
| 17 Feb 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge abutment work completed.Valve chamber work completed.Pack III - out of 8.83km pipeline 7.4km supplied and 4.617km pipe laid. work progress is slow.Notice issued several times to the Contractor Udayapuram Labour contractor Society. Pipe laying work at Culvert ongoing.slow progress.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola column work started. Manjalampuram sump inside plastering completed and outside plastering on progress.Pack 4 part II pipe laying work in progress.GL tank at Velooni side wall reinforcement work completed and form work started. Package-V -Earthing at Substation yard completed as per the direction of electrical inspectorate,Pumpset and transformer supplied on site ,Erection of transformer and pump sets are in progress | Koothuparamba Proj AE 2 |