| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 06 Jun 2023 | Pack 1- work completed, final bill submitted. Pack 2- work completed.harging on balance,Pack III -no progress in pipe laying.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola finshing work on progress,interconnection work on progress.Pack 4 Pumphouse at Vellooni finishing work on progress,interconnection work on progress,Package-V -Finishing work on progress,waiting for safety certification from KSEB | Koothuparamba Proj AE 2 | |
| 01 Jun 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work completed and Interconnection work completed.Pack III -no progress in pipe laying.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola finshing work on progress,interconnection work on progress.Pack 4 Pumphouse at Vellooni finishing work on progress,interconnection work on progress,Package-V -Finishing work on progress,waiting for safety certification from KSEB | Koothuparamba Proj AE 2 | |
| 25 May 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work completed and Interconnection work completed.Pack III -no progress in pipe laying.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola finshing work on progress,interconnection work on progress.Pack 4 part II 300 mm DI pipe 1960m laid and 200 mm DI pipe 1150m laid,work in progress, Pumphouse at Vellooni finishing work on progress,interconnection work on progress,Package-V -Finishing work on progress,waiting for safety certification from KSEB | Koothuparamba Proj AE 2 | |
| 22 May 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work completed and Interconnection work completed.Pack III -no progress in pipe laying.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola finshing work on progress,interconnection work on progress.Pack 4 part II 300 mm DI pipe 1960m laid and 200 mm DI pipe 1150m laid,work in progress, Pumphouse at Vellooni finishing work on progress,interconnection work on progress,Package-V -Finishing work on progress,waiting for safety certification from KSEB | Koothuparamba Proj AE 2 | |
| 17 May 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work completed and Interconnection work completed.Pack III -Pipe laying work slow in progress.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola finshing work on progress,interconnection work on progress.Pack 4 part II 300 mm DI pipe 1960m laid and 200 mm DI pipe 1150m laid,work in progress, Pumphouse at Vellooni finishing work on progress,interconnection work on progress,Package-V -Finishing work on progress,waiting for safety certification from KSEB | Koothuparamba Proj AE 2 | |
| 10 May 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work completed and Interconnection work completed.Pack III -Pipe laying work slow in progress.Pack 4 (part -I) -, pumphouse at Manjalampuram work on progress and poovathinchola finshing work on progress,interconnection work on progress.Pack 4 part II 300 mm DI pipe 1960m laid and 200 mm DI pipe 1150m laid,work in progress, Pumphouse at Vellooni finishing work on progress,interconnection work on progress,Package-V -Finishing work on progress,waiting for safety certification from KSEB | Koothuparamba Proj AE 2 | |
| 04 May 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work completed and pipe laying work started.Pack III -Pipe laying work slow in progress.Pack 4 (part -I) -, pumphouse at Manjalampuram work on progress and poovathinchola roof slab completed,interconnection work on progress.Pack 4 part II 300 mm DI pipe 1960m laid and 200 mm DI pipe 1150m laid,work in progress, Pumphouse at Vellooni slab work started,interconnection work on progress,Package-V - Pump interconnection work ongoing.Fencing work on going,lighting work ongoing | Koothuparamba Proj AE 2 | |
| 28 Apr 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work completed and pipe laying work started.Pack III -Pipe laying work slow in progress.Pack 4 (part -I) -, pumphouse at Manjalampuram work on progress and poovathinchola roof slab completed,interconnection work on progress.Pack 4 part II 300 mm DI pipe 1960m laid and 200 mm DI pipe 1150m laid,work in progress, Pumphouse at Vellooni work started,interconnection work on progress,Package-V -erection of transformer ongoing , termination work ongoing, Pump interconnection work ongoing.Fencing work on going | Koothuparamba Proj AE 2 | |
| 24 Apr 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work completed and pipe laying work started.Pack III -Pipe laying work slow in progress.Pack 4 (part -I) -, pumphouse at Manjalampuram work on progress and poovathinchola roof slab completed.Pack 4 part II 300 mm DI pipe 1960m laid and 200 mm DI pipe 1150m laid,work in progress, Pumphouse at Vellooni work started,Package-V -erection of transformer ongoing , termination work ongoing, Pump interconnection work ongoing.Fencing work on going | Koothuparamba Proj AE 2 | |
| 18 Apr 2023 | Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work completed and pipe laying work started.Pack III -Pipe laying work slow in progress.Pack 4 (part -I) -, pumphouse at Manjalampuram work on progress and poovathinchola roof slab completed.Pack 4 part II 300 mm DI pipe 1960m laid and 200 mm DI pipe 1150m laid,work in progress, Pumphouse at Vellooni work started,Package-V -erection of transformer ongoing , termination work ongoing, Pump interconnection work ongoing. | Koothuparamba Proj AE 2 |