Status Date Overall Project Status Project Officer Contact
06 Jun 2023 Pack 1- work completed, final bill submitted. Pack 2- work completed.harging on balance,Pack III -no progress in pipe laying.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola finshing work on progress,interconnection work on progress.Pack 4 Pumphouse at Vellooni finishing work on progress,interconnection work on progress,Package-V -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2
01 Jun 2023 Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work completed and Interconnection work completed.Pack III -no progress in pipe laying.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola finshing work on progress,interconnection work on progress.Pack 4 Pumphouse at Vellooni finishing work on progress,interconnection work on progress,Package-V -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2
25 May 2023 Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work completed and Interconnection work completed.Pack III -no progress in pipe laying.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola finshing work on progress,interconnection work on progress.Pack 4 part II 300 mm DI pipe 1960m laid and 200 mm DI pipe 1150m laid,work in progress, Pumphouse at Vellooni finishing work on progress,interconnection work on progress,Package-V -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2
22 May 2023 Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work completed and Interconnection work completed.Pack III -no progress in pipe laying.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola finshing work on progress,interconnection work on progress.Pack 4 part II 300 mm DI pipe 1960m laid and 200 mm DI pipe 1150m laid,work in progress, Pumphouse at Vellooni finishing work on progress,interconnection work on progress,Package-V -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2
17 May 2023 Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work completed and Interconnection work completed.Pack III -Pipe laying work slow in progress.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola finshing work on progress,interconnection work on progress.Pack 4 part II 300 mm DI pipe 1960m laid and 200 mm DI pipe 1150m laid,work in progress, Pumphouse at Vellooni finishing work on progress,interconnection work on progress,Package-V -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2
10 May 2023 Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work completed and Interconnection work completed.Pack III -Pipe laying work slow in progress.Pack 4 (part -I) -, pumphouse at Manjalampuram work on progress and poovathinchola finshing work on progress,interconnection work on progress.Pack 4 part II 300 mm DI pipe 1960m laid and 200 mm DI pipe 1150m laid,work in progress, Pumphouse at Vellooni finishing work on progress,interconnection work on progress,Package-V -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2
04 May 2023 Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work completed and pipe laying work started.Pack III -Pipe laying work slow in progress.Pack 4 (part -I) -, pumphouse at Manjalampuram work on progress and poovathinchola roof slab completed,interconnection work on progress.Pack 4 part II 300 mm DI pipe 1960m laid and 200 mm DI pipe 1150m laid,work in progress, Pumphouse at Vellooni slab work started,interconnection work on progress,Package-V - Pump interconnection work ongoing.Fencing work on going,lighting work ongoing Koothuparamba Proj AE 2
28 Apr 2023 Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work completed and pipe laying work started.Pack III -Pipe laying work slow in progress.Pack 4 (part -I) -, pumphouse at Manjalampuram work on progress and poovathinchola roof slab completed,interconnection work on progress.Pack 4 part II 300 mm DI pipe 1960m laid and 200 mm DI pipe 1150m laid,work in progress, Pumphouse at Vellooni work started,interconnection work on progress,Package-V -erection of transformer ongoing , termination work ongoing, Pump interconnection work ongoing.Fencing work on going Koothuparamba Proj AE 2
24 Apr 2023 Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work completed and pipe laying work started.Pack III -Pipe laying work slow in progress.Pack 4 (part -I) -, pumphouse at Manjalampuram work on progress and poovathinchola roof slab completed.Pack 4 part II 300 mm DI pipe 1960m laid and 200 mm DI pipe 1150m laid,work in progress, Pumphouse at Vellooni work started,Package-V -erection of transformer ongoing , termination work ongoing, Pump interconnection work ongoing.Fencing work on going Koothuparamba Proj AE 2
18 Apr 2023 Pack 1- work completed, final bill submitted. Pack 2-Steel bridge work completed and pipe laying work started.Pack III -Pipe laying work slow in progress.Pack 4 (part -I) -, pumphouse at Manjalampuram work on progress and poovathinchola roof slab completed.Pack 4 part II 300 mm DI pipe 1960m laid and 200 mm DI pipe 1150m laid,work in progress, Pumphouse at Vellooni work started,Package-V -erection of transformer ongoing , termination work ongoing, Pump interconnection work ongoing. Koothuparamba Proj AE 2