Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Aug 2023 Package 1- work completed, final bill submitted. Pack 2- work completed.charging on balance,Pack III -DI 100 pipe laying started.Pack 4 (part -I) -Interconnection work completed.fininishing work on progress,Transformer and pump set work are balance,Pack 4 (part II)-interconnection work completed, pump set work are balance,Package-V -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2
10 Aug 2023 Package 1- work completed, final bill submitted. Pack 2- work completed.charging on balance,Pack III -no progress in pipe laying.Pack 4 (part -I) -Interconnection work completed.fininishing work on progress,Transformer and pump set work are balance,Pack 4 (part II)-interconnection work completed, pump set work are balance,Package-V -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2
03 Aug 2023 Package 1- work completed, final bill submitted. Pack 2- work completed.charging on balance,Pack III -no progress in pipe laying.Pack 4 (part -I) -Interconnection work completed.fininishing work on progress,Transformer and pump set work are balance,Pack 4 (part II)-interconnection work completed, pump set work are balance,Package-V -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2
26 Jul 2023 Package 1- work completed, final bill submitted. Pack 2- work completed.charging on balance,Pack III -no progress in pipe laying.Pack 4 (part -I) -Interconnection work completed.Transformer and pump set work are balance,Pack 4 (part II)-interconnection work completed, pump set work are balance,Package-V -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2
19 Jul 2023 Package 1- work completed, final bill submitted. Pack 2- work completed.charging on balance,Pack III -no progress in pipe laying.Pack 4 (part -I) -Interconnection work completed.Transformer and pump set work are balance,Pack 4 (part II)-interconnection work completed, pump set work are balance,Package-V -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2
11 Jul 2023 Package 1- work completed, final bill submitted. Pack 2- work completed.charging on balance,Pack III -no progress in pipe laying.Pack 4 (part -I) -Interconnection work completed.Transformer and pump set work are balance,Pack 4 (part II)-interconnection work completed, pump set work are balance,Package-V -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2
05 Jul 2023 Package 1- work completed, final bill submitted. Pack 2- work completed.charging on balance,Pack III -no progress in pipe laying.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola finshing work on progress,interconnection work on progress.Pack 4 Pumphouse at Vellooni finishing work on progress,interconnection work on progress,Package-V -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2
30 Jun 2023 Package 1- work completed, final bill submitted. Pack 2- work completed.charging on balance,Pack III -no progress in pipe laying.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola finshing work on progress,interconnection work on progress.Pack 4 Pumphouse at Vellooni finishing work on progress,interconnection work on progress,Package-V -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2
23 Jun 2023 Package 1- work completed, final bill submitted. Pack 2- work completed.charging on balance,Pack III -no progress in pipe laying.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola finshing work on progress,interconnection work on progress.Pack 4 Pumphouse at Vellooni finishing work on progress,interconnection work on progress,Package-V -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2
19 Jun 2023 ack 1- work completed, final bill submitted. Pack 2- work completed.charging on balance,Pack III -no progress in pipe laying.Pack 4 (part -I) -, pumphouse at Manjalampuram and poovathinchola finshing work on progress,interconnection work on progress.Pack 4 Pumphouse at Vellooni finishing work on progress,interconnection work on progress,Package-V -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2