Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Jan 2024 Package 1- work completed, final bill submitted. Package 2- work completed, charging work on balance.package 3 - push through work for 300 mm pumping main completed at kelakam police station area and at Manjalampuram town push through work completed for 200 and 300 mm dia pumping main . Tank connection work is on progress , Package 4 (part -I) -Pump set and transformer erection are completed. Waiting for KSEB connection , package 4 (part II)-Pump set erection completed . Waiting for KSEB connection , Package 5 -Waiting for KSEB connection, Pckage 5 II , Ordered for pumpset Koothuparamba Proj AE 2
04 Jan 2024 Package 1- work completed, final bill submitted. Package 2- work completed, charging work on balance.package 3 - push through work for 300 mm pumping main completed at kelakam police station area and at Manjalampuram town push through work completed for 200 and 300 mm dia pumping main . Tank connection work is on progress , Package 4 (part -I) -Pump set and transformer erection are completed. Waiting for KSEB connection , package 4 (part II)-Pump set erection completed . Waiting for KSEB connection , Package 5 -Waiting for KSEB connection, Pckage 5 II , Ordered for pumpset Koothuparamba Proj AE 2
01 Jan 2024 Package 1- work completed, final bill submitted. Package 2- work completed, charging work on balance.package 3 - push through work for 300 mm pumping main completed at kelakam police station area and at Manjalampuram town push through work completed for 200 and 300 mm dia pumping main . Tank connection work is on progress , Package 4 (part -I) -Pump set and transformer erection are completed. Waiting for KSEB connection , package 4 (part II)-Pump set erection completed . Waiting for KSEB connection , Package 5 -Waiting for KSEB connection Koothuparamba Proj AE 2
12 Dec 2023 Package 1- work completed, final bill submitted. Package 2- work completed, charging work on balance.package 3 - push through work for 300 mm pumping main completed at kelakam police station area and at Manjalampuram town push through work is on progress for 200 and 300 mm dia pumping mainPackage 4 (part -I) -Pump set and transformer erection are completed 4 (part II)-Pump set erection completed and finishing work on progress. Package 5 -All the erection work completed and commissioning pending due to delay in getting safety certification from electrical inspectorate Koothuparamba Proj AE 2
03 Nov 2023 Package 1- work completed, final bill submitted. Package 2- work completed, charging work on balance.package 3 - Laying of 200mm MS Pipe on Steel bridge completed and interconnection work for Manjalampuram, Kambipalam and Memala Sump started.Package 4 (part -I) -Pump set and transformer erection on progress,Package 4 (part II)-pumpset erection work on progress. Package 5 -Finishing work on progress,waiting for KSEB connection Koothuparamba Proj AE 2
20 Oct 2023 Package 1- work completed, final bill submitted. Package 2- work completed, charging work on balance.package 3 - Steel bridge work completed .Package 4 (part -I) -Interconnection work completed , Finishing work on progress, Pump set supplied and transformer erection on progress,Package 4 (part II)-pumpset erection work started. Package 5 -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2
19 Oct 2023 Package 1- work completed, final bill submitted. Package 2- work completed, charging work on balance.package 3 - Steel bridge work completed .Package 4 (part -I) -Interconnection work completed , Finishing work on progress, Pump set supplied and transformer erection on progress,Package 4 (part II)-pumpset erection work started. Package 5 -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2
06 Oct 2023 Package 1- work completed, final bill submitted. Package 2- work completed, charging work on balance.package 3 - Steel bridge work started .Package 4 (part -I) -Interconnection work completed , Finishing work on progress, Pump set supplied and transformer erection on progress,Package 4 (part II)-interconnection work completed, pump set supplied. Package 5 -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2
13 Sep 2023 Package 1- work completed, final bill submitted. Pack 2- work completed.charging ongoing.package 3 - pipe laying work on progress .Pack 4 (part -I) -Interconnection work completed.fininishing work on progress,Transformer and pump set work are balance,Pack 4 (part II)-interconnection work completed, pump set work are balance,Package-V -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2
07 Sep 2023 Package 1- work completed, final bill submitted. Pack 2- work completed.charging ongoing.Pack 4 (part -I) -Interconnection work completed.fininishing work on progress,Transformer and pump set work are balance,Pack 4 (part II)-interconnection work completed, pump set work are balance,Package-V -Finishing work on progress,waiting for safety certification from KSEB Koothuparamba Proj AE 2