Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Mar 2024 Package 1- work completed, final bill submitted. Package 2- Charging to be done after getting power connection at Well/Plant .package 3 - Tank connection work in Progress , Package 4 (part -I) - ,Demand notice issued from KSEB for power line extension for Manjalapuram sump and payment completed .Waiting for KSEB connection package 4 (part II)-KSEB Power connection process on going. , Package 5 -Demand note recieved from KSEB for power connection., Pckage 5 II , Pump set supplied Koothuparamba Proj AE 2
11 Mar 2024 Package 1- work completed, final bill submitted. Package 2- Charging to be done after getting power connection at Well/Plant .package 3 - Tank connection work in Progress , Package 4 (part -I) - ,Demand notice issued from KSEB for power line extension for Manjalapuram sump and payment completed .Waiting for KSEB connection package 4 (part II)-KSEB Power connection process on going. , Package 5 -Demand note recieved from KSEB for power connection., Pckage 5 II , Pump set supplied Koothuparamba Proj AE 2
07 Mar 2024 Package 1- work completed, final bill submitted. Package 2- Charging to be done after getting power connection at Well/Plant .package 3 - Tank connection work in Progress , Package 4 (part -I) - ,Demand notice issued from KSEB for power line extension for Manjalapuram sump and payment completed .Waiting for KSEB connection package 4 (part II)-KSEB Power connection process on going. , Package 5 -Demand note recieved from KSEB for power connection., Pckage 5 II , Pump set supplied Koothuparamba Proj AE 2
04 Mar 2024 Package 1- work completed, final bill submitted. Package 2- Charging to be done after getting power connection at Well/Plant .package 3 - Tank connection work in Progress , Package 4 (part -I) - ,Demand notice issued from KSEB for power line extension for Manjalapuram sump and payment completed .Waiting for KSEB connection package 4 (part II)-KSEB Power connection process on going. , Package 5 -Demand note recieved from KSEB for power connection., Pckage 5 II , Pump testing done. Awaiting delivery Koothuparamba Proj AE 2
29 Feb 2024 Package 1- work completed, final bill submitted. Package 2- Charging to be done after getting power connection at Well/Plant .package 3 - Tank connection work in Progress , Package 4 (part -I) - ,Demand notice issued from KSEB for power line extension for Manjalapuram sump and payment completed .Waiting for KSEB connection package 4 (part II)-KSEB Power connection process on going. , Package 5 -Demand note recieved from KSEB for power connection., Pckage 5 II , Pump testing done. Awaiting delivery Koothuparamba Proj AE 2
26 Feb 2024 Package 1- work completed, final bill submitted. Package 2- Charging to be done after getting power connection at Well/Plant .package 3 - Tank connection work in Progress , Package 4 (part -I) - ,Demand notice issued from KSEB for power line extension for Manjalapuram sump and payment completed .Waiting for KSEB connection package 4 (part II)-KSEB Power connection process on going. , Package 5 -Demand note recieved from KSEB for power connection., Pckage 5 II , Pump testing done. Awaiting delivery Koothuparamba Proj AE 2
14 Feb 2024 Package 1- work completed, final bill submitted. Package 2- work completed, charging work on balance.package 3 - Inter connection work is on progress , Package 4 (part -I) - ,Demand notice issued from KSEB for power line extension for Manjalapuram sump and payment completed .Waiting for KSEB connection package 4 (part II)-Pump set erection completed . Waiting for KSEB connection , Package 5 -Waiting for KSEB connection, Pckage 5 II , Testing completed. Ordered for pumpset Koothuparamba Proj AE 2
05 Feb 2024 Project Package 1- work completed, final bill submitted. Package 2- work completed, charging work on balance.package 3 - Inter connection work is on progress , Package 4 (part -I) - ,Demand notice issued from KSEB for power line extension for Manjalapuram sump and payment completed .Waiting for KSEB connection package 4 (part II)-Pump set erection completed . Waiting for KSEB connection , Package 5 -Waiting for KSEB connection, Pckage 5 II , Testing completed. Ordered for pumpset Koothuparamba Proj AE 2
30 Jan 2024 Project Package 1- work completed, final bill submitted. Package 2- work completed, charging work on balance.package 3 - Tank connection work is on progress , Package 4 (part -I) -Pump set and transformer erection are completed. Waiting for KSEB connection , package 4 (part II)-Pump set erection completed . Waiting for KSEB connection , Package 5 -Waiting for KSEB connection, Pckage 5 II , Ordered for pumpset Koothuparamba Proj AE 2
23 Jan 2024 Package 1- work completed, final bill submitted. Package 2- work completed, charging work on balance.package 3 - push through work for 300 mm pumping main completed at kelakam police station area and at Manjalampuram town push through work completed for 200 and 300 mm dia pumping main . Tank connection work is on progress , Package 4 (part -I) -Pump set and transformer erection are completed. Waiting for KSEB connection , package 4 (part II)-Pump set erection completed . Waiting for KSEB connection , Package 5 -Waiting for KSEB connection, Pckage 5 II , Ordered for pumpset Koothuparamba Proj AE 2