Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Jul 2024 30.50 km distribution completed out of 36.5 km and 1485 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. .FHTC and Chamber work in progress... Kollam Project HD
11 Jul 2024 30.50 km distribution completed out of 36.5 km and 1485 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Earth work excavation for concrete restoration ...Connection work and Valve fixing work in progress... Kollam Project HD
10 Jul 2024 30.50 km distribution completed out of 36.5 km and 1485 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Earth work excavation for concrete restoration ...Connection work and Geotagging progress... Kollam Project HD
09 Jul 2024 30.50 km distribution completed out of 36.5 km and 1485 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Fhtc and Interconnection work in progress...Restoration and DI gap closing work in progress... Kollam Project HD
08 Jul 2024 30.50 km distribution completed out of 36.5 km and 1417 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed..Earthwork for cc work at Paravur-Varkala road...Connection work and geotagging progress... Kollam Project HD
07 Jul 2024 30.50 km distribution completed out of 36.5 km and 1417 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Road restoration work and Interlock work in progress... Kollam Project HD
06 Jul 2024 30.50 km distribution completed out of 36.5 km and 1357 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Road restoration work and connection work in progress... Kollam Project HD
05 Jul 2024 30.50 km distribution completed out of 36.5 km and 1357 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Out side - Side wall concrete chipping work in progress @Pukkulam Ohsr...Connection work and road concrete work in progress Kollam Project HD
04 Jul 2024 30.50 km distribution completed out of 36.5 km and 1357 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Connection work an d Geotagging progress... Kollam Project HD
03 Jul 2024 30.50 km distribution completed out of 36.5 km and 1357 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Fhtc and geotagging progress.. Kollam Project HD