| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 12 Jul 2024 | 30.50 km distribution completed out of 36.5 km and 1485 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. .FHTC and Chamber work in progress... | Kollam Project HD | |
| 11 Jul 2024 | 30.50 km distribution completed out of 36.5 km and 1485 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Earth work excavation for concrete restoration ...Connection work and Valve fixing work in progress... | Kollam Project HD | |
| 10 Jul 2024 | 30.50 km distribution completed out of 36.5 km and 1485 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Earth work excavation for concrete restoration ...Connection work and Geotagging progress... | Kollam Project HD | |
| 09 Jul 2024 | 30.50 km distribution completed out of 36.5 km and 1485 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Fhtc and Interconnection work in progress...Restoration and DI gap closing work in progress... | Kollam Project HD | |
| 08 Jul 2024 | 30.50 km distribution completed out of 36.5 km and 1417 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed..Earthwork for cc work at Paravur-Varkala road...Connection work and geotagging progress... | Kollam Project HD | |
| 07 Jul 2024 | 30.50 km distribution completed out of 36.5 km and 1417 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Road restoration work and Interlock work in progress... | Kollam Project HD | |
| 06 Jul 2024 | 30.50 km distribution completed out of 36.5 km and 1357 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Road restoration work and connection work in progress... | Kollam Project HD | |
| 05 Jul 2024 | 30.50 km distribution completed out of 36.5 km and 1357 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Out side - Side wall concrete chipping work in progress @Pukkulam Ohsr...Connection work and road concrete work in progress | Kollam Project HD | |
| 04 Jul 2024 | 30.50 km distribution completed out of 36.5 km and 1357 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Connection work an d Geotagging progress... | Kollam Project HD | |
| 03 Jul 2024 | 30.50 km distribution completed out of 36.5 km and 1357 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Fhtc and geotagging progress.. | Kollam Project HD |