| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 Jun 2024 | 28.50 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed.... .Interconnection progress...Fhtc and Htc work in progress.... | Kollam Project HD | |
| 10 Jun 2024 | 28.50 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed.... .Interconnection progress...Laying, Fhtc and Geotagging progress... | Kollam Project HD | |
| 09 Jun 2024 | 26.70 km distribution completed out of 36.5 km and 1248 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed.... ..Interlock restoration and Htc work in progress .. | Kollam Project HD | |
| 08 Jun 2024 | 26.70 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed.... ..Interlock restoration work in progress ..Htc And Fhtc wprk in progress.. | Kollam Project HD | |
| 07 Jun 2024 | 26.70 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed.... Connection work and geotagging progress...Interlock restoration work in progress at ward 9 and 31 | Kollam Project HD | |
| 06 Jun 2024 | 26.70 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Connection work and geotagging progress... | Kollam Project HD | |
| 05 Jun 2024 | 26.70 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Fhtc and htc work in progress...Road restoration work in progress... | Kollam Project HD | |
| 04 Jun 2024 | 26.70 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Fhtc and htc work in progress...Road restoration work in progress... | Kollam Project HD | |
| 03 Jun 2024 | 26.70 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Excavation and laying progress...Road restoration and htc work in progress..Geotagging progress... | Kollam Project HD | |
| 02 Jun 2024 | 26.70 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Excavation and laying progress...Road restoration and interlock work in progress... | Kollam Project HD |