Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Aug 2024 32 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ... Fhtc and concrete breaking progress..Backfilling progress... Kollam Project HD
15 Aug 2024 31.50 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ....Sidewall cleaning and Inside column painting work in progress @ Pukkulam Ohsr Kollam Project HD
14 Aug 2024 31.50 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed Geotagging progress... painting progress @ Pukkulam ohsr tank Kollam Project HD
13 Aug 2024 31.50 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ... Concrete restoration and connection work in progress... Kollam Project HD
12 Aug 2024 31.50 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ... Concrete restoration and Interconnection work in progress... Kollam Project HD
11 Aug 2024 31.50 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ... Chamber work & Interconnection work in progress... Kollam Project HD
09 Aug 2024 31.50 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ... Chamber work & Laying work in progress...Backfilling progress... Kollam Project HD
08 Aug 2024 31.50 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ...Fhtc and Interconnection work in progress... Kollam Project HD
07 Aug 2024 31.50 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ...Chamber cover slab fixing work in progress .. Fhtc and geotagging progress... Kollam Project HD
06 Aug 2024 31.50 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ... Concrete restoration and fhtc work in progress.. Kollam Project HD