| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 18 Aug 2024 | 32 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ... Fhtc and concrete breaking progress..Backfilling progress... | Kollam Project HD | |
| 15 Aug 2024 | 31.50 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ....Sidewall cleaning and Inside column painting work in progress @ Pukkulam Ohsr | Kollam Project HD | |
| 14 Aug 2024 | 31.50 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed Geotagging progress... painting progress @ Pukkulam ohsr tank | Kollam Project HD | |
| 13 Aug 2024 | 31.50 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ... Concrete restoration and connection work in progress... | Kollam Project HD | |
| 12 Aug 2024 | 31.50 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ... Concrete restoration and Interconnection work in progress... | Kollam Project HD | |
| 11 Aug 2024 | 31.50 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ... Chamber work & Interconnection work in progress... | Kollam Project HD | |
| 09 Aug 2024 | 31.50 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ... Chamber work & Laying work in progress...Backfilling progress... | Kollam Project HD | |
| 08 Aug 2024 | 31.50 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ...Fhtc and Interconnection work in progress... | Kollam Project HD | |
| 07 Aug 2024 | 31.50 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ...Chamber cover slab fixing work in progress .. Fhtc and geotagging progress... | Kollam Project HD | |
| 06 Aug 2024 | 31.50 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ... Concrete restoration and fhtc work in progress.. | Kollam Project HD |