| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Jun 2024 | 28.50 km distribution completed out of 36.5 km and 1357 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed... Connection work and Interlock replacing progress...Geotagging parogress... | Kollam Project HD | |
| 20 Jun 2024 | No work due to rain | Kollam Project HD | |
| 19 Jun 2024 | No work due to rain | Kollam Project HD | |
| 18 Jun 2024 | 28.50 km distribution completed out of 36.5 km and 1357 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed...Fhtc and Htc work in progress...Interconnection and Geotagging progress... | Kollam Project HD | |
| 17 Jun 2024 | 28.50 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed... Geotagging works in progress... | Kollam Project HD | |
| 16 Jun 2024 | 28.50 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.Interlock replacing .and concrete restoration works in progress... Excavation and leak work in progress... | Kollam Project HD | |
| 15 Jun 2024 | 28.50 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed....Connection work and leak work in progress... | Kollam Project HD | |
| 14 Jun 2024 | 28.50 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed....Interconnection and backfilling works in progress....Geotagging progress... | Kollam Project HD | |
| 13 Jun 2024 | 28.50 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.... .Interlock restoration and fhtc work progress..Backfilling progress... | Kollam Project HD | |
| 12 Jun 2024 | 28.50 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.... .Interconnection and Fhtc work in progress... | Kollam Project HD |