Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Jun 2024 28.50 km distribution completed out of 36.5 km and 1357 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed... Connection work and Interlock replacing progress...Geotagging parogress... Kollam Project HD
20 Jun 2024 No work due to rain Kollam Project HD
19 Jun 2024 No work due to rain Kollam Project HD
18 Jun 2024 28.50 km distribution completed out of 36.5 km and 1357 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed...Fhtc and Htc work in progress...Interconnection and Geotagging progress... Kollam Project HD
17 Jun 2024 28.50 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed... Geotagging works in progress... Kollam Project HD
16 Jun 2024 28.50 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.Interlock replacing .and concrete restoration works in progress... Excavation and leak work in progress... Kollam Project HD
15 Jun 2024 28.50 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed....Connection work and leak work in progress... Kollam Project HD
14 Jun 2024 28.50 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed....Interconnection and backfilling works in progress....Geotagging progress... Kollam Project HD
13 Jun 2024 28.50 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.... .Interlock restoration and fhtc work progress..Backfilling progress... Kollam Project HD
12 Jun 2024 28.50 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.... .Interconnection and Fhtc work in progress... Kollam Project HD