| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Jun 2024 | 26.70 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Road restoration and interconnection work in progress... | Kollam Project HD | |
| 31 May 2024 | 26.70 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Road restoration work in progress... | Kollam Project HD | |
| 30 May 2024 | 26.70 km distribution completed out of 36.5 km and 1179 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..fhtc work in progress.. | Kollam Project HD | |
| 29 May 2024 | 26.70 km distribution completed out of 36.5 km and 1129 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Leak rectification and Geotagging progress... | Kollam Project HD | |
| 28 May 2024 | No work due to heavy rain. | Kollam Project HD | |
| 27 May 2024 | 26.70 km distribution completed out of 36.5 km and 1129 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed....Road restoration progress...@ ward 16 | Kollam Project HD | |
| 25 May 2024 | 26.70 km distribution completed out of 36.5 km and 1129 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed....Road restoration progress...@Varkkala road.. | Kollam Project HD | |
| 24 May 2024 | 26.70 km distribution completed out of 36.5 km and 1129 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed....Road restoration progress... | Kollam Project HD | |
| 23 May 2024 | No work due to heavy rain | Kollam Project HD | |
| 22 May 2024 | 26.70 km distribution completed out of 36.5 km and 1129 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Excavation and laying progress...Road restoration progress... | Kollam Project HD |