Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 May 2024 26.70 km distribution completed out of 36.5 km and 1129 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Excavation and laying progress...FHTC and HTC work in progress...Road restoration progress...@ Paravoor to Varkkala Road. Kollam Project HD
18 May 2024 26.70 km distribution completed out of 36.5 km and 1129 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Excavation and laying progress...Interconnection and Tagging works in progress...FHTC and HTC work in progress... Kollam Project HD
17 May 2024 26.70 km distribution completed out of 36.5 km and 1129 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Excavation and laying progress...Interconnection and Tagging works in progress... Kollam Project HD
16 May 2024 26.70 km distribution completed out of 36.5 km and 1129 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed...Fhtc and tagging progress...Excavation and backfilling progress.. Kollam Project HD
15 May 2024 25.5 km distribution completed out of 36.5 km and 1117 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed...Connection workin progress..FHTC and Geotagging progress...Interconnection completed in ward 31 Kollam Project HD
14 May 2024 25.5 km distribution completed out of 36.5 km and 1117 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed....Laying and FHTC work in progress...Geotagging and road restoration progress... Kollam Project HD
13 May 2024 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed....Interconnection work in progress...Laying and FHTC work in progress...Geotagging progress.. Kollam Project HD
11 May 2024 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed.....FHTC and Laying work in progress.. backfilling and Geotagging progress... Kollam Project HD
10 May 2024 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed.....FHTC and Laying work in progress.. backfilling and Geotagging progress... Kollam Project HD
09 May 2024 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Interconnection progress @ ward 5...FHTC and Laying work in progress..Geotagging progress... Kollam Project HD