| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 May 2024 | 26.70 km distribution completed out of 36.5 km and 1129 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Excavation and laying progress...FHTC and HTC work in progress...Road restoration progress...@ Paravoor to Varkkala Road. | Kollam Project HD | |
| 18 May 2024 | 26.70 km distribution completed out of 36.5 km and 1129 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Excavation and laying progress...Interconnection and Tagging works in progress...FHTC and HTC work in progress... | Kollam Project HD | |
| 17 May 2024 | 26.70 km distribution completed out of 36.5 km and 1129 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Excavation and laying progress...Interconnection and Tagging works in progress... | Kollam Project HD | |
| 16 May 2024 | 26.70 km distribution completed out of 36.5 km and 1129 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed...Fhtc and tagging progress...Excavation and backfilling progress.. | Kollam Project HD | |
| 15 May 2024 | 25.5 km distribution completed out of 36.5 km and 1117 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed...Connection workin progress..FHTC and Geotagging progress...Interconnection completed in ward 31 | Kollam Project HD | |
| 14 May 2024 | 25.5 km distribution completed out of 36.5 km and 1117 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed....Laying and FHTC work in progress...Geotagging and road restoration progress... | Kollam Project HD | |
| 13 May 2024 | 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed....Interconnection work in progress...Laying and FHTC work in progress...Geotagging progress.. | Kollam Project HD | |
| 11 May 2024 | 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed.....FHTC and Laying work in progress.. backfilling and Geotagging progress... | Kollam Project HD | |
| 10 May 2024 | 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed.....FHTC and Laying work in progress.. backfilling and Geotagging progress... | Kollam Project HD | |
| 09 May 2024 | 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Interconnection progress @ ward 5...FHTC and Laying work in progress..Geotagging progress... | Kollam Project HD |