| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 20 Dec 2024 | Distribution 35.5 out of 36.5km completed and 2823 nos FHTCs completed out of 4122. FHTCs ....fhtc work in progress...Tar works progress. Chamber works in progress..Part 2 work progress...65%. 6.1 km laid out of 6.5 km scope...Concrete restoration and interlock restoration work in progress... | Kollam Project HD | |
| 19 Dec 2024 | Distribution 35.5 out of 36.5km completed and 2798 nos FHTCs completed out of 4122. FHTCs ....fhtc work in progress...Tar works progress. Chamber works in progress..Part 2 work progress...65%. 6.1 km laid out of 6.5 km scope...Concrete restoration and interlock restoration work in progress... | Kollam Project HD | |
| 18 Dec 2024 | Distribution 35.5 out of 36.5km completed and 2798 nos FHTCs completed out of 4122. FHTCs ....fhtc work in progress...Tar works progress. Chamber works in progress..Part 2 work progress...65%. 5.8 km laid out of 6.5 km scope...Concrete restoration and interlock restoration work in progress... | Kollam Project HD | |
| 17 Dec 2024 | Distribution 35.5 out of 36.5km completed and 2798 nos FHTCs completed out of 4122. FHTCs ....fhtc work in progress...Tar works progress...part 2 work progress...65%. 5.5 km laid out of 6.5 km scope...Concrete restoration and interlock restoration work in progress... | Kollam Project HD | |
| 16 Dec 2024 | Distribution 35.5 out of 36.5km completed and 2798 nos FHTCs completed out of 4122. FHTCs ....fhtc work in progress...Tar works progress...part 2 work progress...65%. 5.5 km laid out of 6.5 km scope...Concrete restoration and interlock restoration work in progress... | Kollam Project HD | |
| 20 Oct 2024 | 34.5 km distribution completed out of 36.5 km and fhtcs 2267 completed out of 4122 and second work :1.2 km completed out of 6.5 km | Kollam Project HD | |
| 19 Oct 2024 | 34.5 km distribution completed out of 36.5 km and fhtcs 2267 completed out of 4122 and second work :1.2 km completed out of 6.5 km | Kollam Project HD | |
| 17 Oct 2024 | 34.5 km distribution completed out of 36.5 km and 2137 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed .. Fhtc and Geotagging progress... | Kollam Project HD | |
| 16 Oct 2024 | 34 km distribution completed out of 36.5 km and 2037 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed .. Fhtc and Geotagging progress... | Kollam Project HD | |
| 15 Oct 2024 | 34 km distribution completed out of 36.5 km and 2037 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed .. Interconnection and chamber work in progress....Geotagging progress... | Kollam Project HD |