Overall Project Status

Status Date Overall Project Status Project Officer Contact
20 Dec 2024 Distribution 35.5 out of 36.5km completed and 2823 nos FHTCs completed out of 4122. FHTCs ....fhtc work in progress...Tar works progress. Chamber works in progress..Part 2 work progress...65%. 6.1 km laid out of 6.5 km scope...Concrete restoration and interlock restoration work in progress... Kollam Project HD
19 Dec 2024 Distribution 35.5 out of 36.5km completed and 2798 nos FHTCs completed out of 4122. FHTCs ....fhtc work in progress...Tar works progress. Chamber works in progress..Part 2 work progress...65%. 6.1 km laid out of 6.5 km scope...Concrete restoration and interlock restoration work in progress... Kollam Project HD
18 Dec 2024 Distribution 35.5 out of 36.5km completed and 2798 nos FHTCs completed out of 4122. FHTCs ....fhtc work in progress...Tar works progress. Chamber works in progress..Part 2 work progress...65%. 5.8 km laid out of 6.5 km scope...Concrete restoration and interlock restoration work in progress... Kollam Project HD
17 Dec 2024 Distribution 35.5 out of 36.5km completed and 2798 nos FHTCs completed out of 4122. FHTCs ....fhtc work in progress...Tar works progress...part 2 work progress...65%. 5.5 km laid out of 6.5 km scope...Concrete restoration and interlock restoration work in progress... Kollam Project HD
16 Dec 2024 Distribution 35.5 out of 36.5km completed and 2798 nos FHTCs completed out of 4122. FHTCs ....fhtc work in progress...Tar works progress...part 2 work progress...65%. 5.5 km laid out of 6.5 km scope...Concrete restoration and interlock restoration work in progress... Kollam Project HD
20 Oct 2024 34.5 km distribution completed out of 36.5 km and fhtcs 2267 completed out of 4122 and second work :1.2 km completed out of 6.5 km Kollam Project HD
19 Oct 2024 34.5 km distribution completed out of 36.5 km and fhtcs 2267 completed out of 4122 and second work :1.2 km completed out of 6.5 km Kollam Project HD
17 Oct 2024 34.5 km distribution completed out of 36.5 km and 2137 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed .. Fhtc and Geotagging progress... Kollam Project HD
16 Oct 2024 34 km distribution completed out of 36.5 km and 2037 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed .. Fhtc and Geotagging progress... Kollam Project HD
15 Oct 2024 34 km distribution completed out of 36.5 km and 2037 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed .. Interconnection and chamber work in progress....Geotagging progress... Kollam Project HD