| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 31 Aug 2024 | 33 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ...Level Guage fixed at pukkulam ohsr...Geotagging progress... | Kollam Project HD | |
| 28 Aug 2024 | 33 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ... Interconnection and Valve chamber works in progress... | Kollam Project HD | |
| 27 Aug 2024 | 33 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ... Interconnection and laying progress...Geotagging progress... | Kollam Project HD | |
| 25 Aug 2024 | 33 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ... Interconnection work in progress... | Kollam Project HD | |
| 24 Aug 2024 | 33 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ...FHTC and Laying work in progress... | Kollam Project HD | |
| 23 Aug 2024 | 32.5 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ...FHTC and Laying work in progress... | Kollam Project HD | |
| 22 Aug 2024 | 32.5 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ...FHTC, Laying and Interconnection work in progress... | Kollam Project HD | |
| 21 Aug 2024 | 32 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ...FHTC, Laying and Interconnection work in progress... | Kollam Project HD | |
| 20 Aug 2024 | 32 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ... Fhtc , Laying and concrete breaking progress.. | Kollam Project HD | |
| 19 Aug 2024 | 32 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ... Fhtc and Interconnection work in progress... | Kollam Project HD |