| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 23 Jul 2024 | 31 km distribution completed out of 36.5 km and 1678 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ...Tank painting work in progress... | Kollam Project HD | |
| 22 Jul 2024 | 31 km distribution completed out of 36.5 km and 1678 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ...Tank painting work under progress... Geotagging progress... | Kollam Project HD | |
| 21 Jul 2024 | 30.50 km distribution completed out of 36.5 km and 1485 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - completed.. Interconnection work in progress....earth work excavation for concrete restoration | Kollam Project HD | |
| 20 Jul 2024 | 30.50 km distribution completed out of 36.5 km and 1485 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Restoration and FHTC work in progress.. | Kollam Project HD | |
| 19 Jul 2024 | 30.50 km distribution completed out of 36.5 km and 1572 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Connection work and interlock restoration work in progress... | Kollam Project HD | |
| 18 Jul 2024 | 30.50 km distribution completed out of 36.5 km and 1485 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Connection work and Concrete restoration progress ...Sidewall plastering and concrete chipping progress @ pookkulam OHSR | Kollam Project HD | |
| 17 Jul 2024 | No work due to heavy rain | Kollam Project HD | |
| 16 Jul 2024 | 30.50 km distribution completed out of 36.5 km and 1485 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. Earth work excavation progress for road restoration.. chamber work in progress @ Varkkala -Paravoor road .. Geotagging progress... | Kollam Project HD | |
| 15 Jul 2024 | 30.50 km distribution completed out of 36.5 km and 1485 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. .FHTC and Geotagging progress... | Kollam Project HD | |
| 13 Jul 2024 | 30.50 km distribution completed out of 36.5 km and 1485 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work in progress .. JICA GAP CLOSING works - 95% completed.. .FHTC and Chamber work in progress... | Kollam Project HD |