| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Aug 2024 | 31.50 km distribution completed out of 36.5 km and 1863 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ... Interlock restoration work in progress...Connection work and road restoration progress... | Kollam Project HD | |
| 02 Aug 2024 | 31.50 km distribution completed out of 36.5 km and 1824 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ... Connection work & Geotagging progress... | Kollam Project HD | |
| 01 Aug 2024 | 31.50 km distribution completed out of 36.5 km and 1806 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ... Connection work & Geotagging progress... | Kollam Project HD | |
| 31 Jul 2024 | 31 km distribution completed out of 36.5 km and 1778 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ... Connection work & Ohsr painting works in progress.... | Kollam Project HD | |
| 30 Jul 2024 | No work due to rain | Kollam Project HD | |
| 29 Jul 2024 | 31 km distribution completed out of 36.5 km and 1778 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ... Fhtc and Geotagging progress... | Kollam Project HD | |
| 27 Jul 2024 | 31 km distribution completed out of 36.5 km and 1778 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ... Fhtc and Geotagging progress....Painting work progress@ Pookkulam Ohsr | Kollam Project HD | |
| 26 Jul 2024 | 31 km distribution completed out of 36.5 km and 1778 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ...Restoration and Fhtc work in progress...Painting work progress@ Pookkulam Ohsr | Kollam Project HD | |
| 25 Jul 2024 | 31 km distribution completed out of 36.5 km and 1778 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ...Restoration and Fhtc work in progress... | Kollam Project HD | |
| 24 Jul 2024 | 31 km distribution completed out of 36.5 km and 1778 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works - Completed ...Fhtc work in progress... | Kollam Project HD |