AMRUT 2.0 - Providing house connections and distribution network in Paravoor Municipality
| Project |
AMRUT 2.0 - Providing house connections and distribution network in Paravoor Municipality |
| Project Code |
KLMAMRUT112213227 |
| Type |
Main project |
| Funding Agency |
AMRUT |
| Category |
AMRUT |
| Type of scheme |
Water Supply |
| Scheme |
AMRUT |
| Description |
works including JICA gap closing works , line extension and 4122 house connection works |
| Status |
On-going |
| District |
Kollam |
| Executing Office |
Kollam Project Dn |
| AS Amount (Rs) |
163200000
|
| AS Number |
G.O.(Rt)No.2906/2022/LSGD |
| TS Amount (Rs) |
128700000 |
| TS Number |
ORDER No. WRD/KWA-CE(SR)/EST_TS/610/2022_26_1_1 Dated: 07-01-2023 |
| Total Bill Submitted (Rs) |
45349699 |
| Total Bill Paid (Rs) |
45349699 |
| Population Benefitted |
49000 |
| Capacity in MLD |
9.00 |
| Actual Project Completion Date |
11 Dec 2024 |
| Coverage |
entire Paravoor municipality |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
AMRUT 2.0 - Providing house connections and distribution network in Paravoor Municipality |
Kollam Project Dn |
|
| 2 |
AMRUT 2.0 Water Supply Project at Paravoor Municipality PART 2 - work - for laying additional distribution for complete saturation -Pipeline Work |
Kollam Project Dn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 20 Dec 2024 |
Distribution 35.5 out of 36.5km completed and 2823 nos FHTCs completed out of 4122. FHTCs ....fhtc work in progress...Tar works progress. Chamber works in progress..Part 2 work progress...65%. 6.1 km laid out of 6.5 km scope...Concrete restoration and interlock restoration work in progress... |
Kollam Project HD |
|
| 19 Dec 2024 |
Distribution 35.5 out of 36.5km completed and 2798 nos FHTCs completed out of 4122. FHTCs ....fhtc work in progress...Tar works progress. Chamber works in progress..Part 2 work progress...65%. 6.1 km laid out of 6.5 km scope...Concrete restoration and interlock restoration work in progress... |
Kollam Project HD |
|
| 18 Dec 2024 |
Distribution 35.5 out of 36.5km completed and 2798 nos FHTCs completed out of 4122. FHTCs ....fhtc work in progress...Tar works progress. Chamber works in progress..Part 2 work progress...65%. 5.8 km laid out of 6.5 km scope...Concrete restoration and interlock restoration work in progress... |
Kollam Project HD |
|
| 17 Dec 2024 |
Distribution 35.5 out of 36.5km completed and 2798 nos FHTCs completed out of 4122. FHTCs ....fhtc work in progress...Tar works progress...part 2 work progress...65%. 5.5 km laid out of 6.5 km scope...Concrete restoration and interlock restoration work in progress... |
Kollam Project HD |
|
| 16 Dec 2024 |
Distribution 35.5 out of 36.5km completed and 2798 nos FHTCs completed out of 4122. FHTCs ....fhtc work in progress...Tar works progress...part 2 work progress...65%. 5.5 km laid out of 6.5 km scope...Concrete restoration and interlock restoration work in progress... |
Kollam Project HD |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
31/01/2022 |
| Scheduled date of Completion of the Project |
11 Dec 2024 |
| Expected date of Completion |
30/11/2024 |
Processing Dates
| AS Date |
24 Nov 2022 |
| TS Date |
07 Jan 2023 |