| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 19 Sep 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed .. concrete restoration and Chamber work in progress... | Kollam Project HD | |
| 18 Sep 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed .. Connection work in progress... | Kollam Project HD | |
| 17 Sep 2024 | No work due to Onam Holidays | Kollam Project HD | |
| 13 Sep 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed .. Road restoration and Fhtc work in progress... | Kollam Project HD | |
| 12 Sep 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ...Concrete restoration and interlock restoration progress... Geotagging progress ... | Kollam Project HD | |
| 11 Sep 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ...Concrete restoration and geotagging progress... | Kollam Project HD | |
| 05 Sep 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed .... Interconnection and Laying progress... | Kollam Project HD | |
| 04 Sep 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ....Geotagging progress.... | Kollam Project HD | |
| 03 Sep 2024 | 33.5 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed .... Geotagging progress... concrete breaking progress... | Kollam Project HD | |
| 02 Sep 2024 | 33.5 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed .... Geotagging progress... Laying and Interconnection progress... | Kollam Project HD |