| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Oct 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ...Concrete restoration work in progress...Interconnection work in progress.... | Kollam Project HD | |
| 30 Sep 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ....Interconnection work in progress...Concrete restoration work in progress... | Kollam Project HD | |
| 29 Sep 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ....Interconnection work in progress...Laying work in progress...concrete restoration work in progress... | Kollam Project HD | |
| 28 Sep 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ....Interconnection work in progress...Laying work in progress...concrete restoration work in progress... | Kollam Project HD | |
| 27 Sep 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ....Interconnection work in progress...Laying work in progress...Interconnection work in progress... | Kollam Project HD | |
| 26 Sep 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ....Connection work and Chamber work in progress.. | Kollam Project HD | |
| 26 Sep 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ....Connection work and Road restoration progress.. work in progress.. | Kollam Project HD | |
| 23 Sep 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed .. connection work and Chamber work in progress... | Kollam Project HD | |
| 22 Sep 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed .. connection work and Chamber top cover fixing work in progress... | Kollam Project HD | |
| 20 Sep 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed .. connection work and Chamber form work in progress... | Kollam Project HD |