| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 14 Oct 2024 | 34 km distribution completed out of 36.5 km and 1978 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed .. Concrete restoration and geotagging progress... | Kollam Project HD | |
| 13 Oct 2024 | 34 km distribution completed out of 36.5 km and 1978 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed .. Interconnection work in progress... | Kollam Project HD | |
| 12 Oct 2024 | 34 km distribution completed out of 36.5 km and 1978 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed .. Concrete restoration and Interconnection work in progress... | Kollam Project HD | |
| 11 Oct 2024 | 34 km distribution completed out of 36.5 km and 1978 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed .. Fhtc and laying works in progress...Interlock restoration and Interconnection work in progress... | Kollam Project HD | |
| 10 Oct 2024 | 34 km distribution completed out of 36.5 km and 1978 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed . Excavation and laying work in progress...Interlock restoration work in progress... | Kollam Project HD | |
| 08 Oct 2024 | 34 km distribution completed out of 36.5 km and 1978 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed . Interlock restoration progress...Leak work in progress... | Kollam Project HD | |
| 06 Oct 2024 | 34 km distribution completed out of 36.5 km and 1978 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed . concrete restoration and interlock restoration progress... | Kollam Project HD | |
| 05 Oct 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed . concrete restoration and Interconnection progress... | Kollam Project HD | |
| 04 Oct 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed . concrete restoration progress... | Kollam Project HD | |
| 03 Oct 2024 | 34 km distribution completed out of 36.5 km and 1877 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and Column plastering work completed and Floor plastering work completed.. JICA GAP CLOSING works Completed ...earth work excavation for concrete restoration and concrete restoration progress... | Kollam Project HD |