| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 25 Apr 2024 | 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed...Laying and connection work in progress... | Kollam Project HD | |
| 24 Apr 2024 | 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed....Fhtc and Laying work in progress...Backfilling progress.. | Kollam Project HD | |
| 23 Apr 2024 | 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed | Kollam Project HD | |
| 22 Apr 2024 | Work in progress..-24.96 km out of 36.5...Excavation and laying work in progress...Fhtc work in progress....SIde wall.Plastering work progress at Pukkulam Ohsr | Kollam Project HD | |
| 21 Apr 2024 | Work in progress..-24.96 km out of 36.5...Excavation and laying work in progress...Fhtc work in progress..... | Kollam Project HD | |
| 20 Apr 2024 | Work in progress..-24.96 km out of 36.5...Excavation and laying work in progress...Fhtc work in progress..... | Kollam Project HD | |
| 19 Apr 2024 | Work in progress..-24.96 km out of 36.5...Connection work in progress.. | Kollam Project HD | |
| 18 Apr 2024 | Work in progress..-24.96 km out of 36.5...Connection work in progress...Interconnection progress... | Kollam Project HD | |
| 17 Apr 2024 | Work in progress..-24.96 km out of 36.5...Connection work in progress... | Kollam Project HD | |
| 16 Apr 2024 | Work in progress..-24.96 km out of 36.5.. Fhtc and Geotagging progress... | Kollam Project HD |