Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 May 2024 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed...FHTC and Laying work in progress..Geotagging progress... Kollam Project HD
07 May 2024 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Interconnection work in progress...Excavation and laying progress.. FHTC work in progress..Geotagging and Backfilling progress... Kollam Project HD
06 May 2024 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Interconnection work in progress... HTC and FHTC work in progress...Excavation and laying progress.. Kollam Project HD
04 May 2024 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed... FHTC and ..Excavation and laying progress... Kollam Project HD
03 May 2024 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed... FHTC and ..Excavation and laying progress...Interconnection progress... Kollam Project HD
02 May 2024 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed...Excavation and laying work in progress..FHTC work progress @ ward 4,5,6..Connection shifting work in progress at varkkala road. Kollam Project HD
30 Apr 2024 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed...Excavation and laying work in progress..FHTC and Interconnection progress@ ward 5..Leak work in progress... Kollam Project HD
29 Apr 2024 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed...Excavation and laying work in progress..FHTC and Interconnection progress...Concrete breaking progress... Kollam Project HD
28 Apr 2024 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed...Excavation and laying work in progress....FHTC and backfilling work in progress.... Kollam Project HD
27 Apr 2024 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed...Interconnection and FHTc workin progress... Kollam Project HD