| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 08 May 2024 | 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed...FHTC and Laying work in progress..Geotagging progress... | Kollam Project HD | |
| 07 May 2024 | 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Interconnection work in progress...Excavation and laying progress.. FHTC work in progress..Geotagging and Backfilling progress... | Kollam Project HD | |
| 06 May 2024 | 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed..Interconnection work in progress... HTC and FHTC work in progress...Excavation and laying progress.. | Kollam Project HD | |
| 04 May 2024 | 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed... FHTC and ..Excavation and laying progress... | Kollam Project HD | |
| 03 May 2024 | 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed... FHTC and ..Excavation and laying progress...Interconnection progress... | Kollam Project HD | |
| 02 May 2024 | 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed...Excavation and laying work in progress..FHTC work progress @ ward 4,5,6..Connection shifting work in progress at varkkala road. | Kollam Project HD | |
| 30 Apr 2024 | 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed...Excavation and laying work in progress..FHTC and Interconnection progress@ ward 5..Leak work in progress... | Kollam Project HD | |
| 29 Apr 2024 | 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed...Excavation and laying work in progress..FHTC and Interconnection progress...Concrete breaking progress... | Kollam Project HD | |
| 28 Apr 2024 | 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed...Excavation and laying work in progress....FHTC and backfilling work in progress.... | Kollam Project HD | |
| 27 Apr 2024 | 25.5 km distribution completed out of 36.5 km and 912 fhtcs completed out of 4122 fhtcs , Tank renovation works - Rcc works completed and plastering work progressing, JICA GAP CLOSING works - 95% completed...Interconnection and FHTc workin progress... | Kollam Project HD |