| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 15 Apr 2024 | Work in progress..-24.96 km out of 36.5...Fhtc and Geotagging progress.. | Kollam Project HD | |
| 13 Apr 2024 | Work in progress..-24.96 km out of 36.5...Fhtc, Excavation and laying progress...Backfilling progress... | Kollam Project HD | |
| 12 Apr 2024 | Work in progress..-24.96 km out of 36.5...Excavation and laying progress...Fhtc and Geotagging progress... | Kollam Project HD | |
| 11 Apr 2024 | Work in progress..-24.96 km out of 36.5....Side wall inside plastering work in progress @Pukkulam Tank... Fhtc work in progress... | Kollam Project HD | |
| 09 Apr 2024 | Work in progress..-24.96 km out of 36.5....Fhtc work in progress...Material Shifting work is in progress at Pukkulam tank site for plastering... | Kollam Project HD | |
| 08 Apr 2024 | Work in progress..-24.96 km out of 36.5....Fhtc , Interconnection and concrete breaking progress... | Kollam Project HD | |
| 07 Apr 2024 | Work in progress..-24.96 km out of 36.5....Excavation and laying progress...Fhtc and Geotagging progress... | Kollam Project HD | |
| 06 Apr 2024 | Work in progress..-24.96 km out of 36.5....Excavation and laying progress...Fhtc and Geotagging progress... | Kollam Project HD | |
| 05 Apr 2024 | Work in progress..-24.96 km out of 36.5....Excavation and laying progress...Fhtc and Geotagging progress...GI work and backfilling progress... | Kollam Project HD | |
| 04 Apr 2024 | Work in progress..-24.96 km out of 36.5....Excavation and laying progress...Fhtc and Geotagging progress...GI work and backfilling progress... | Kollam Project HD |