Status Date Overall Project Status Project Officer Contact
30 May 2022 58 percentage completed. Concentrate sump and thicked sludge sump PCC completed. 65 m3 rcc proposed today. reinforcement for sludge holding tank , T sump is also proposed today Kollam Project HD
29 May 2022 58 percentage completed. Concentrate sump and thicked sludge sump PCC completed. 65 m3 rcc proposed today postponed due to material shortage...Equalization tank side wall 2nd lift form work in progress(95% completed)...air blower room footings earth excavation work in progress Kollam Project HD
29 May 2022 57 %completed...65 m3 rcc proposed today postponed due to material shortage...Equalization tank side wall 2nd lift form work in progress(95% completed)...air blower room footings earth excavation work in progress Kollam Project HD
26 May 2022 All major components first lift RCC completed except MBBR 1,2, ) , sludge holding tank , pretreatment units, centrifuge building,Sludge thickner a. MBBR 3- Second lift RCC completed , b. Sludge thickner - RCC raftcompleted . c. secondary clarifier no.2 - up to sidewall first lift rcc completed d.Secondary clarifier no. 1 - upto sidewall RCC 2.4 m completed. e. MBBR IV - first lift sidewall rcc completed f. MBBR I- ready for first lift sidewall rcc ( material shortage). g. MBBR II - raft completed, first side wall shuttering work 50 percentage completed , h. equilization tank -first sidewall RCC completed , ready for second lift rcc ( materials shortage) i. septage tank -final lift completed. j. Sludge holding tank - PCC completed . k. CCT -upto first sidewall completed & work for walkway in progress. l. Chlorine room - upto roof completed, plastering almost completed. m. Blower room footing work partially pcc completed n pretreatment units pcc partially completed O. Thickened sludge sump - excavation started and in progress P. Concentrate sump - excavation started and in progress Kollam Project HD
25 May 2022 MBBR 1 side wall form work completed...,MBBR 2 side wall 1st lift form work in progress..., Equalization tank side wall 2nd lift form work in progress..., centrate sump & thickned sludge sump earth excavation work in progress Kollam Project HD
24 May 2022 MBBR 2 side wall 1st lift form work in progress..., Equalization tank side wall 2nd lift form work in progress..., centrate sump & thickned sludge sump earth excavation work in progress Kollam Project HD
23 May 2022 MBBR 2 side wall 1st lift form work in progress..., Equalization tank side wall 2nd lift form work in progress..., Chlorine room parapet side wall plastering work in progress. centrate sump & thickned sludge sump earth excavation work in progress Kollam Project HD
22 May 2022 MBBR 2 side wall 1st lift form work in progress..., Equalization tank side wall 2nd lift form work in progress Kollam Project HD
21 May 2022 MBBR 1 side wall getting ready for rcc..,MBBR 2 side wall 1st lift form work in progress..., Equalization tank side wall 2nd lift form work in progress..., Chlorine room parapet side wall plastering work in progress Kollam Project HD
20 May 2022 Equalization tank side wall 2nd lift form work in progress..,MBBR 1 side wall form work in progress (Completed 90%)..,MBBR 2 side wall form work started..., Kollam Project HD