| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 22 Jun 2022 | MBBR 1 side wall second lift form work in progress..,Sludge shed earth excavation work in progress..,clarifier 1 side wall water proofing work in progress | Kollam Project HD | |
| 21 Jun 2022 | MBBR 1 side wall second lift form work in progress...,MBBR 2 side wall first lift deshuttering work in progress..,clarifier 1 hydro test water filling work in progress | Kollam Project HD | |
| 20 Jun 2022 | 61 % completed...,Equalization tank center wall shuttering work in progress...,MBBR1 second lift side wall form work in progress..,Equalization tank side wall,MBBR 2 side wall,T-sump raft curing work in progress..,sludge holding tank side wall reinforcement work in progress | Kollam Project HD | |
| 15 Jun 2022 | Sludge shed footings earth excavation work in progress..,sludge thickner side wall reinforcement work in progress..,air blower room part footing & column reinforcement work in progress | Kollam Project HD | |
| 11 Jun 2022 | Air Blower room part footing rcc work completed...,balance portion earth excavation work in progress..,sludge thickner side wall reinforcement work in progress...,septage tank water filling work in progress(for hydro test process) | Kollam Project HD | |
| 04 Jun 2022 | 59 % completed..,Clarifier 2 - Launder reinforcement work in progress...,MBBR 1 - 2nd lift side wall reinforcement work in progress...,Air blower room footing steel making work in progress | Kollam Project HD | |
| 03 Jun 2022 | 59 % completed..,MBBR 2 - 1st lift Side wall form work in progress..,T-Sump - raft reinforcement work in progress..,Clarifier 2 - Launder reinforcement work in progress...,MBBR 1 - 2nd lift side wall reinforcement work in progress...,Air blower room footing steel making work in progress | Kollam Project HD | |
| 02 Jun 2022 | MBBR 2 - 1st lift Side wall form work in progress..,T-Sump - raft reinforcement work in progress..,Clarifier 2 - Launder reinforcement & Form work in progress...,MBBR 1 - 1st lift side wall curing work in progress...,Air blower room - footing pit bottom earth leveling work in progress | Kollam Project HD | |
| 01 Jun 2022 | 59 percentage completed .Thickend sludge sump raft reinforcement work in progress. MBBR 2 side wall form work in progress ..., Clarifier 1 launder form work & reinforcement work in progress | Kollam Project HD | |
| 31 May 2022 | 59 percentage completed. Concentrate sump and thicked sludge sump raft reinforcement work in progress. MBBR 1 side wall rcc work completed..., Clarifier 12 launder reinforcement work in progress | Kollam Project HD |