Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Jun 2022 MBBR 1 side wall second lift form work in progress..,Sludge shed earth excavation work in progress..,clarifier 1 side wall water proofing work in progress Kollam Project HD
21 Jun 2022 MBBR 1 side wall second lift form work in progress...,MBBR 2 side wall first lift deshuttering work in progress..,clarifier 1 hydro test water filling work in progress Kollam Project HD
20 Jun 2022 61 % completed...,Equalization tank center wall shuttering work in progress...,MBBR1 second lift side wall form work in progress..,Equalization tank side wall,MBBR 2 side wall,T-sump raft curing work in progress..,sludge holding tank side wall reinforcement work in progress Kollam Project HD
15 Jun 2022 Sludge shed footings earth excavation work in progress..,sludge thickner side wall reinforcement work in progress..,air blower room part footing & column reinforcement work in progress Kollam Project HD
11 Jun 2022 Air Blower room part footing rcc work completed...,balance portion earth excavation work in progress..,sludge thickner side wall reinforcement work in progress...,septage tank water filling work in progress(for hydro test process) Kollam Project HD
04 Jun 2022 59 % completed..,Clarifier 2 - Launder reinforcement work in progress...,MBBR 1 - 2nd lift side wall reinforcement work in progress...,Air blower room footing steel making work in progress Kollam Project HD
03 Jun 2022 59 % completed..,MBBR 2 - 1st lift Side wall form work in progress..,T-Sump - raft reinforcement work in progress..,Clarifier 2 - Launder reinforcement work in progress...,MBBR 1 - 2nd lift side wall reinforcement work in progress...,Air blower room footing steel making work in progress Kollam Project HD
02 Jun 2022 MBBR 2 - 1st lift Side wall form work in progress..,T-Sump - raft reinforcement work in progress..,Clarifier 2 - Launder reinforcement & Form work in progress...,MBBR 1 - 1st lift side wall curing work in progress...,Air blower room - footing pit bottom earth leveling work in progress Kollam Project HD
01 Jun 2022 59 percentage completed .Thickend sludge sump raft reinforcement work in progress. MBBR 2 side wall form work in progress ..., Clarifier 1 launder form work & reinforcement work in progress Kollam Project HD
31 May 2022 59 percentage completed. Concentrate sump and thicked sludge sump raft reinforcement work in progress. MBBR 1 side wall rcc work completed..., Clarifier 12 launder reinforcement work in progress Kollam Project HD