No.KWA/PDK/DB3-866/2018 Vol.IV dated 18.06.24
23/06/2024 | File: letter to ABM& Hydrotech- 18.06.24.pdf |
Download
Delay in progress
No. KWA/PHC/Q/D1-1867/2018 Dated: 21.06.2024
23/06/2024 | File: letter to hydrotech.pdf |
Download
Letter to contractor for speed up the work. ( MoM dated 16.05.2024 chaired by SE, PHC Kollam is also attached with )
fifith EOT
06/05/2023 | File: ETOC-Order5th.pdf |
Download
No: KWA/PHC/Q/D1-1867/2018 Dated: 03.05.2023
Progress report as on 20/04/2023
25/04/2023 | File: Stp progress reporting as on 20.04.23.pdf |
Download
Slow progress of work-letter dated 13/04/2023
25/04/2023 | File: KWA-PHC-Q-D1-1867-2018.pdf |
Download
Recommendation to issue termination notice -Letter to SE dated 12/04/2023
25/04/2023 | File: STP Termination notice -reg (1).pdf |
Download
Minutes of the meeting(03/04/2023)
25/04/2023 | File: STP MoM dated 3.04.23.pdf |
Download
Poor progress in work-letter dated 30/03/2023
25/04/2023 | File: STP letter to the contractor (1).pdf |
Download
Letter to contractor regarding inordinate delay achieving progress-letter dated 31/03/2023
25/04/2023 | File: poor prrogress - meeting intimation.pdf |
Download
Transformer vendor approval - mail dated 21/03/2023
25/04/2023 | File: Gmail - 12 MLD STP at kureepuzha transformer vendor approval - reg-.pdf |
Download
Delay in arranging works-mail dated 01/02/2023
25/04/2023 | File: Gmail - AMRUT -12 MLD STP at Kureepuzha -delay in arranging works -reg-.pdf |
Download
Delay in work progress -letter dated 28/01/2023
25/04/2023 | File: delay in work progress.pdf |
Download
Delay in work progress -Remedial action , mail dated :14/12/2022
25/04/2023 | File: Gmail - 12 MLD STP at Kureepuzha - Arranging more workforce and materials -reg -.pdf |
Download
Revised technical data sheet of EM components
25/04/2023 | File: Revised technical data sheet of EM components.pdf |
Download
Revised technical data sheet of EM components -letter dated 09/12/2022
Demand received from GWD
22/03/2023 | File: Adobe Scan Mar 20, 2023 (3).pdf |
Download
STP power point presentation dated 18.1.2023
19/01/2023 | File: stp power point dated 18-01-2023 (1).pdf |
Download
STP power point dated 6.01.2023
06/01/2023 | File: stp power point dated 06.01.2023.pdf |
Download
Scheme
23/12/2022 | File: 2D822AA0-04E9-41B0-A270-34BCC72F27DC.jpeg |
Download
Progress ppt
23/12/2022 | File: stp power point dated 8.12.22-2.pdf |
Download
Progress ppt
23/12/2022 | File: stp power point dated 8.12.22-2.pdf |
Download
Revised Schedule
10/11/2022 | File: 12 MLD STP micro schedule 15.09.2022 (1) (1).pdf |
Download
STP progress vs scheduled RCC
10/11/2022 | File: STP RCC Progress as on 9.11.22.pdf |
Download
Time extension order
09/11/2022 | File: STP-TOC-3.pdf |
Download
No: KWA/PHC/Q/D1-1867/2018 Dated 5.11.2022
Notice to the contractor dated 26.10.2022 for slow progress
26/10/2022 | File: Gmail - Urgent attention- 12 MLD STP at Kureepuzha - slow progress of the work -Reg_- (1).pdf |
Download
Notice to the contractor
26/10/2022 | File: Gmail - Urgent Attention. - 12MLD STP at kureepuzha - regarding filling of all tanks -reg__.pdf |
Download
Intimation to the contractor - Schedule prepared by KWA to commission by DEC.2022
20/10/2022 | File: Gmail - STP - Detailed work schedule.pdf |
Download
Revised schedule chart -
20/10/2022 | File: Graph (1).pdf |
Download
Revised schedule prepared as 14.10.2022
20/10/2022 | File: stp progress schedule 14.10.22.pdf |
Download
Notice to the contractor dated 12.10.2022 for speed up the work and commission by December 2022
20/10/2022 | File: stp.pdf |
Download
Schedule submitted upto march 2023- not acceptable notice dated 11.10.2022
20/10/2022 | File: not acceptable.pdf |
Download
Meeting intimation - 03.10.2022 for slow progress
20/10/2022 | File: meeting intimation stp.pdf |
Download
Notice to the contractor dated 30.09.2022 for slow progress
20/10/2022 | File: STP Notice.pdf |
Download
KW A/PDK/DB3-866/2018 Vol II
Revised schedule as on 21.09.22
22/09/2022 | File: stp progress as on 21.09.2022.pdf |
Download
Time extension with out LD
12/09/2022 | File: Time extension with out LD.pdf |
Download
Minutes of the meeting(30-07-2022)
10/08/2022 | File: Minutes-STP.pdf |
Download
letter to contractor - to achieving progress
10/08/2022 | File: 08-08-2022(letter to contractor - to achieving progress).jpg |
Download
Revised schedule upto september 2022
04/08/2022 | File: STP reschedule.pdf |
Download
Direction to the contractor for redesign - components
13/07/2022 | File: stp redesign reg.pdf |
Download
TIME EXTENSION ORDER WITH LD
28/06/2022 | File: STP Time extension.pdf |
Download
Letter to the Contractor - delay in work progress
18/05/2022 | File: letter to abm (1)_compressed (1).pdf |
Download
Letter to the contractor dated 12.04.2022
20/04/2022 | File: STP Kureepuzha.pdf |
Download
SHOW CAUSE NOTICE-issued to the contractor dated 25.03.2022
26/03/2022 | File: show cause_220326_081408.pdf |
Download
Delay Analysis - Action to be taken
25/03/2022 | File: stp delay analysis.pdf |
Download
Minutes of Meeting conducted at STP site by Managing Director,KWA
09/03/2022 | File: Scan10004-220309-003341.pdf |
Download
Microschedule for month -march
01/03/2022 | File: microschedule -march.xlsx |
Download
Revised Schedule
01/03/2022 | File: STP REVISED Schedule 1.3.22.xlsx |
Download
Elevation & Section details of Admin Building
16/02/2022 | File: elevation and section detail of admin building.jpg |
Download
Plan Elevation & Section of Admin Building
16/02/2022 | File: plan elevation and section detail of admin building_11zon.jpg |
Download
Structure Detail of Admin Building
16/02/2022 | File: structure deatilof admin building ( slab and column footing & staircase_11zon.jpg |
Download
GA Drawing of Septage Tank I & II and Plant Room
16/02/2022 | File: GA Drwaing of septage tank I and II and plant room_11zon.jpg |
Download
GA Drawing of Cascade Aerator
16/02/2022 | File: GA drawing of cascade aerator_11zon.jpg |
Download
Structural Details Of Cascade Aerator
16/02/2022 | File: structural details of cascade aerator.jpg |
Download
Plan Elevation & Section Detail of MCC Building
16/02/2022 | File: plan elevation and section details of MCC building_11zon.jpg |
Download
Plan Detail Of Pre Treatment Unit
16/02/2022 | File: plan detail of pre treatment unit_11zon.jpg |
Download
Structure Detail Of Pre Treatment unit Footing & Slab
16/02/2022 | File: structural detail of pre treatment unit footingand slab_11zon.jpg |
Download
Structure Detail Of Wall Section & Beam of Pre Treatment Unit
16/02/2022 | File: structural detail of wall section and beam of pre treatment unit_11zon.jpg |
Download
GA Drawing of Equalization Tank
16/02/2022 | File: GA drawing of equalization tank.jpg |
Download
Detail of MBBR Tank I,II,III,IV
16/02/2022 | File: detail pf MBBR tank 1234.jpg |
Download
Structural details of MBBR Tank I,II,III,IV
16/02/2022 | File: Structural detail of MBBR tank 1234_11zon.jpg |
Download
Structural details of Clarifier Tank
16/02/2022 | File: structural detail of clarifier tank_11zon.jpg |
Download
Plan Elevation & Section details of Chlorination Room & Tonner Shed
16/02/2022 | File: plan elevation and section detail of chlorination room and tonner shed_11zon.jpg |
Download
Structural details of Tonner & Chlorination Room
16/02/2022 | File: structuaral detail of tonner and chlorination room_11zon.jpg |
Download
Plan Elevation & Section details of Chlorine Contact Tank
16/02/2022 | File: plan elevation and section detail of chlorination room and tonner shed_11zon.jpg |
Download
Structural details of Chlorine Contact Tank
16/02/2022 | File: Structural detials of achlorine contact tank.jpg |
Download
Plan & Section details of Sludge Holding Tank & Pump house
16/02/2022 | File: plan and section detail ofsludge pump house_11zon.jpg |
Download
Structural Details of Sludge Holding Tank & Pump house
16/02/2022 | File: structural detials sludge holding tank and sludge pump house_11zon.jpg |
Download
Plan Elevation & Section of Sludge Shed
16/02/2022 | File: plan elevationand section details of sludge shed_11zon - Copy.jpg |
Download
Structure detail of Sludge Shed
16/02/2022 | File: structural deatil of sludge shed_11zon.jpg |
Download
Plan Elevation & Section of Sludge Thickener
16/02/2022 | File: plan elevationand section details of sludge shed_11zon - Copy.jpg |
Download
Structure detail of Sludge Thickener
16/02/2022 | File: Structural detail of sludge thickener.jpg |
Download
Plan Elevation & Section of Air Blower Room
16/02/2022 | File: Plan elevation and section detail of air blower room.jpg |
Download
Structure detail of Air Blower
16/02/2022 | File: structure detail of air blower.jpg |
Download
Letter to contractor -Show cause notice issuing-delay in progress
27/01/2022 | File: notice.pdf |
Download
Letter to contractor -Show cause notice issuing-delay in progress
27/01/2022 | File: letter to speed up work to ABM.pdf |
Download
File No: 1425/A2/2021/KCZMA The CRZ clearance was issued by KCZMA on 28.04.2012. The CRZ clearance issued will remain valid for a period of 7 years, as per 4.2 (i) h (V) of CRZ notification, and it can be extended by a maximum of three years. Mom dated 8.11.2021….The validity of CRZ Clearance will expire on 28.04.2022.
01/12/2021 | File: 117th Minutes KCZMA.pdf |
Download
File No: 1425/A2/2021/KCZMA
The CRZ clearance was issued by KCZMA on 28.04.2012.
The CRZ clearance issued will remain valid for a period of
7 years, as per 4.2 (i) h (V) of CRZ notification, and it can
be extended by a maximum of three years. The validity of
CRZ Clearance will expire on 28.04.2022.
Approved layout by Corporation kollam
22/10/2021 | File: EXTERNAL ROAD.pdf |
Download
KCZMA letter to KWA
29/09/2021 | File: KCZMA LETTER TO KWA.pdf |
Download
Letter to CRZ from Corporation secretary
29/09/2021 | File: letter from secretary kollam to crz.pdf |
Download
Letter from District Town planner Kollam
29/09/2021 | File: letter from dtp kollam.pdf |
Download
initial levels
24/09/2021 | File: initial levels stp(1).pdf |
Download
letter from Hon. Mayor, Kollam Corporation
20/08/2021 | File: STP letter from Mayor.pdf |
Download
layout
20/08/2021 | File: 02.LAYOUT PLAN-Model.pdf |
Download
layout proposed
20/08/2021 | File: 02.LAYOUT PLAN-Model.pdf |
Download
ORDER No. TS/2018-2019/2018/9433 Dated: 13-09-2018
20/08/2021 | File: TS.pdf |
Download
ORDER No. TS/2018-2019/2018/9433 Dated: 13-09-2018
Wet land Clearance
27/11/2020 | File: STP_Wetland Clearance.pdf |
Download
Wet land Clearance
clearance from Kerala Pollution Control Board
27/11/2020 | File: STP_Consent to Establish-Upto03-04-2022.pdf |
Download
clearance from Kerala Pollution Control Board
CRZ clearance
27/11/2020 | File: STP_CRZ Clearance.JPG |
Download
TS
26/11/2020 | File: TS.pdf |
Download
ORDER No. TS/2018-2019/2018/9433 Dated: 13-09-2018
A S No.G.O (Rt)No.1169/2020/LSGD dated TVM 17/06/2020
15/07/2020 | File: A S of Kureepuzha S T P.pdf |
Download
A S Amount Rs. 30,0000000.00/-
Revised AS Amount - Rs. 31,91,88,678/-
T S Amount - 29,86,90,000/-