| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 19 Apr 2022 | Equilization tank ...side wall form work in progress..Chlorine room ...Parappet wall plastering work in progress...MBBR 4 ...side wall 2nd lift reinforcement work in progress....Compound wall... primer coating work in progress...MBBR III... sidewall second lift ready for rcc.. | Kollam Project HD | |
| 17 Apr 2022 | RCC is proposed on 18.4.2022 for MBBR 3 and Septage tank last lift. Work for Equalization tank form work in progress | Kollam Project HD | |
| 16 Apr 2022 | MBBR 4 side wall 2nd lift reinforcement work in progress..,Equilization tank side wall form work in progress..,MBBR 3 side wall 2nd lift final form work in progress..,compound wall primer coating work in progress | Kollam Project HD | |
| 15 Apr 2022 | MBBR 3 side wall 2nd lift form work nearing completion..,MBBR 4 side wall 2nd lift reinforcement work in progress..,equilization tank side wall form work in progress.. | Kollam Project HD | |
| 14 Apr 2022 | Sludge holding tank - Excavation completed and ready for PCC , PCC planned today. MBBR 3 2nd lift , Equilization tank sidewall works , Septage tank sidewall works in progress | Kollam Project HD | |
| 13 Apr 2022 | Equilization tank sidewall first lift form work in progress...MBBR III sidewall second lift form work in progress..MBBR IV sidewall second lift reinforcement work started | Kollam Project HD | |
| 12 Apr 2022 | Clarifier 1 side wall deshuttering work in progress..,MBBR 3 side wall 2nd lift form work in progress...,Sludge holding tank earth excavation work in progress...,septage tank side wall final lift reinforcement work in progress | Kollam Project HD | |
| 11 Apr 2022 | Clarifier 1 side wall rcc work completed..,MBBR 3 side wall 2nd lift form work in progress...,CCT walk way reinforcement work in progress...,Sludge holding tank earth excavation work in progress | Kollam Project HD | |
| 10 Apr 2022 | Clarifier 1 side wall rcc work in progress..,MBBR 3 side wall 2nd lift form work in progress | Kollam Project HD | |
| 09 Apr 2022 | clarifier 2 launder form work in progress..,,,MBBR 3 side wall 2nd lift form work in progress..., | Kollam Project HD |