| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 03 Jul 2022 | Work for pretreatment unit pcc completed. Sludge holding tank cleared for reinforcement but stopped. Work for MBBR 4, 2 sidewall reinforcement work in progress. Sludge thickener sidewall form work in progress. | Kollam Project HD | |
| 02 Jul 2022 | Sludge thickener ... sidewall first lift shuttering work in progress...Sludge holding tank dewatering and cleaning progress...MBBR II ..sidewall second lift shuttering progress... | Kollam Project HD | |
| 01 Jul 2022 | Thickned sludge sump side wall form work in progress.., Sludge thickener sidewall form work in progress...MBBR II second lift reinforcement work in progress... | Kollam Project HD | |
| 30 Jun 2022 | MBBR 4 side wall second lift form work in progress...,Thickned sludge sump side wall form work in progress.., Sludge thickener sidewall form work in progress...MBBR II second lift reinforcement work in progress..., | Kollam Project HD | |
| 29 Jun 2022 | Thickned sludge sump side wall form work in progress.., Sludge thickener sidewall form work in progress...MBBR II..second lift reinforcement work in progress. | Kollam Project HD | |
| 28 Jun 2022 | Sludge thickener..sidewall form work in progress...MBBR II..second lift reinforcement work in progress...AIR Blower room..short column rcc work.. | Kollam Project HD | |
| 27 Jun 2022 | Sludge thickner side wall form work in progress....,sludge shed footing pcc completed...,MBBR 1 side wall second lift rcc work completed...,MBBR 2 side wall second lift reinforcement work in progress | Kollam Project HD | |
| 25 Jun 2022 | Sludge shed earth excavation work in progress..,Air blower room part short column reinforcement & form work in progress..,MBBR 1 side wall second lift form work in progress..,sludge thickner side wall form work in progress | Kollam Project HD | |
| 24 Jun 2022 | Sludge pump house earth excavation work in progress..,Air blower room part short column reinforcement & form work in progress..,MBBR 1 side wall second lift form work in progress | Kollam Project HD | |
| 23 Jun 2022 | Sludge shed earth excavation work in progress..,clarifier 1 out side earth filling work in progress...,Air blower room part short column reinforcement & form work in progress | Kollam Project HD |