| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 25 Jul 2022 | Pre-Treatment unit raft beam side form work in progress..,Centrate sump raft reinforcement work in progress...,Sludge shed plinth bottom earth filling work in progress..,septage pump house footing reinforcement work & form work in progress | Kollam Project HD | |
| 24 Jul 2022 | Equalization tank third lift Baffle wall reinforcement work in progress...,Sludge holding tank side wall reinforcement work in progress..,sludge thickner side wall second lift reinforcement work in progress | Kollam Project HD | |
| 23 Jul 2022 | Sludge holding tank.Sidewall... reinforcement work in progress...Sludge thickener side wall.. second lift reinforcement work in progress...Sludge shed ..part footing excavation work in progress... Clarifier 2 sidewall.. second lift form work in progress..Clarifier control chamber side wall form work in progress... MBBR 1.. chamber sidewall form work in progress...Equilization tank buffle wall third lift reinforcement work in progress..(1.2M) Air blower room plinth beam ready for concrete. | Kollam Project HD | |
| 22 Jul 2022 | 1.Pre-Treatment unit - Raft Rcc work in progress 2.Air Blower Room - Plinth Beam form work in progress 3.Thickned Sludge Sump - Second lift Side wall reinforcement work in progress 4.Sludge Holding Tank - Side Wall reinforcement work in progress 5.Sludge Thickner - Side Wall second Lift reinforcement work in progress. 6.Sludge Shed - Plinth Bottom earth filling work in progress | Kollam Project HD | |
| 21 Jul 2022 | Works for all structures included in hydraulic flow .. footing work completed 1. Rcc sidewall of sludge thickener completed 2. Sludge holding tank footings work completed 3. Mbbr no. 2 sidewall rcc work 2 nd lift completed 4. Sludge shed all footings rcc and part short column work completed | Kollam Project HD | |
| 20 Jul 2022 | 1.Sludge Thickner - Side wall rcc work completed. 2.MBBR 2 - Side wall second lift rcc work completed 3.Equalization Tank - Baffle Wall 1st Lift rcc work completed(1.2 M) 4.Sludge Holding Tank - Raft rcc Work completed. 5.Air Blower Room - Plinth Beam reinforcement work in progress 6.Pre-Treatment Unit - Raft reinforcement work nearing completion 7.Clarifier Control Chamber - Raft rcc completed..,wall reinforcement work in progress | Kollam Project HD | |
| 19 Jul 2022 | 1.MBBR 1 Baffle wall,MBBR 2 Second lift side wall,Equilization tank Baffle wall(first lift),Sludge Thickner side wall,Clarifier control chamber raft,Sludge shed part footings & column RCC work in progress 2.Sludge Holding Tank - Raft & wall vertical bar reinforcement work completed..,side wall starter form work in progress. 3.Pre-Treatment Unit - Raft & Column Reinforcement work in progress | Kollam Project HD | |
| 18 Jul 2022 | 1.Sludge holding tank - Raft reinforcement work completed & wall reinforcement work in progress. 2.MBBR 1 buffle wall reinforcement work in progress 3.Sludge shed -Short Column & T -Sump side wall rcc work completed. 4.Pre-treatment unit - Raft reinforcement work in progress 5.Clarifier side wall earth filling work in progress | Kollam Project HD | |
| 16 Jul 2022 | 1.Pre-treatment unit - Raft reinforcement work in progress. 2.Sludge holding tank - Raft reinforcement work completed & wall reinforcement work in progress. 3.MBBR 4 side wall reinforcement work in progress 4.Sludge shed -Short Column setting out work & form work in progress | Kollam Project HD | |
| 15 Jul 2022 | 1.Pre-treatment unit - Raft reinforcement work in progress. 2.Sludge holding tank - Raft reinforcement work in progress. 3.Air blower room - Plinth PCC Plinth beam steel making work in progress 4.Sludge shed - Footing & column reinforcement work in progres | Kollam Project HD |