Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Mar 2022 secondary clarifier no.2 - up to sidewall first lift rcc completed, Secondary clarifier no. 1 - upto raft completed and sidewall reinforcement in progress. MBBR IV - first lift sidewall rcc completed , MBBR III, II & I - raft rcc completed, equilization tank -raft completed , septage tank - upto first sidewall completed. sludge thickner- ready for raft rcc, Sludge holding tank excavation started. CCT -upto first sidewall completed & work for walkway in progress. Chlorine room - upto roof completed, plastering in progress Kollam Project HD
25 Mar 2022 MBBR III side wall first lift form work in progress..sludge thickener raft reinforcement work completed..Clarifier no 1 side wall form work in progress..Clarifier no 2 side wall curing work in progress...Equilization tank side wall reinforcement work started.Sludge holding tank earth excavation work started.& Septage tank 2nd lift side wall reinforcement work started Kollam Project HD
24 Mar 2022 MBBR III.. wall first lift form work in progress..sludge thickener..raft reinforcement work in progress..Clarifier no 1..wall inside form work started..Clarifier no 2..wall first lift curing in progress... Kollam Project HD
23 Mar 2022 Clarifier 2 1st lift ... curing work in progress...Sludge thickner raft reinforcement work in progress..,MBBR 4 wall 2nd lift shuttering work in progress....,CCT 2nd lift wall and walk way form work in progress...Chlorine room inside plastering in progress..septage tank ..sidewall deshuttering work. MBBR III..sidewall first lift shuttering work in progress.. Kollam Project HD
22 Mar 2022 Clarifier 2 1st lift wall rcc work completed & curing work in progress...Sludge thickner raft reinforcement work in progress..,MBBR 4 wall 2nd lift reinforcement work in progress....,CCT 2nd lift wall and walk way form work in progres Kollam Project HD
21 Mar 2022 Clarifier 2 1st lift wall rcc work in progress...,sludge thickner raft reinforcement work in progress..,septage tank 1st lift wall form work in progress....,CCT 2nd lift wall and walk way form work in progress.. Kollam Project HD
19 Mar 2022 CC 3 and part bill amount released to the contractor. Work for clarifier sidewall rcc is scheduled today afternoon. Shuttering works MBBR no.3 and Septage tank in final stage for side wall rcc Kollam Project HD
18 Mar 2022 Equilization tank wall steel making work..Septage tank wall form work in progress...Equilization tank raft curing work in progress... Kollam Project HD
17 Mar 2022 Septage tank wall form work in progress...., Equilization tank raft curing work in progress..., MMBR-I wall reinforcement work in progress.... Kollam Project HD
16 Mar 2022 Septage tank wall form work in progress...., Equilization tank raft curing work in progress..., Clarifier-I wall reinforcement work in progress.... Kollam Project HD