Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Apr 2022 Form work for Launder inside clarifier 2 ...,Form work for side wall of MBBR 3 continues...,Earth excavation for sludge holding tank nearing completion..,clarifier 1 side wall is ready for rcc Kollam Project HD
07 Apr 2022 Clarifier 1 side wall form work in progress..,MBBR 3 side wall curing work & deshuttering work in progress.....,Sludge holding tank earth excavation work in progress Kollam Project HD
06 Apr 2022 Sludge holding tank earth excavation work in progress...,Clarifier 1 side wall form work in progress....,MBBR 3 side wall curing & deshuttering work in progress...,septage tank 2nd lift wall getting ready for concrete Kollam Project HD
05 Apr 2022 Sludge thickener ..raft rcc completed..curing in progress..MBBR III ..sidewall deshuttering work ..Secondary Clarifier no 1..sidewall form work in progress... Kollam Project HD
04 Apr 2022 MBBR 3 Sidewall RCC started today early morning and in progress. Also Sludge thickner Raft RCC in progress Kollam Project HD
03 Apr 2022 Sludge thickner - RCC part completed. Balance postponed due to rain secondary clarifier no.2 - up to sidewall first lift rcc completed, Secondary clarifier no. 1 - upto raft completed and sidewall reinforcement in progress. MBBR IV - first lift sidewall rcc completed , MBBR III - raft completed ready for side wall RCC completed MBBR II & I - raft rcc & reinforcement completed, equilization tank -raft completed , septage tank - upto first sidewall completed, second lift sidewall ready for RCC Sludge holding tank excavation started. CCT -upto first sidewall completed & work for walkway in progress. Chlorine room - upto roof completed, plastering in progress Kollam Project HD
02 Apr 2022 CCT walk way and sidewall form work in progress...Clarifier 1...sidewall form work in progress..Equilization tank side wall reinforcement work..MBBR II ...sidewall reinforcement work in progress...MBBR III..side wall ready for concrete... Kollam Project HD
01 Apr 2022 Equilization tank side wall reinforcement work in progress...,CCT walk way & side wall form work in progress..,MBBR 2 side wall reinforcement work in progress..,MBBR 3 side wall & sludge thickner raft ready for concrete Kollam Project HD
31 Mar 2022 Sludge holding tank earth excavation work in progress...Storage tank second lift wall form work in progress...MBBR 2 side wall reinforcement work.. Kollam Project HD
30 Mar 2022 Secondary clarifier shuttering in progress. Equilization tank reinforcement sidewall, Septage tank sidewall shuttering, CCT walkway reinforcement and shuttering… Kollam Project HD