Status Date Overall Project Status Project Officer Contact
17 May 2022 Equalization tank side wall 2nd lift form work in progress...;MBBR 1 side wall 1st lift form work in progress. Kollam Project HD
16 May 2022 Equalization tank side wall 2nd lift form work in progress...;MBBR 1 side wall 1st lift form work in progress. Kollam Project HD
14 May 2022 MBBR 1 side wall 1st lift form work in progres..,internal road earth cutting work in progress Kollam Project HD
13 May 2022 air blower room footings earth excavation work in progress..,pre-treatment unit part pcc work in progress..,MBBR 1 side wall 1st lift form work in progress Kollam Project HD
12 May 2022 Air blower room footings earth excavation work in progress..,chlorine room parapet wall plastering work in progress...,internal road work started Kollam Project HD
11 May 2022 57 %completed. All major components first lift RCC completed except MBBR 1,2, ) , sludge holding tank , pretreatment units, centrifuge building,Sludge thickner a. MBBR 3- Second lift RCC completed , b. Sludge thickner - RCC raftcompleted . c. secondary clarifier no.2 - up to sidewall first lift rcc completed d.Secondary clarifier no. 1 - upto sidewall RCC 2.4 m completed. e. MBBR IV - first lift sidewall rcc completed f. MBBR III - second lift sidewall completed . g. MBBR II & I - raft rcc & reinforcement completed, h. equilization tank -sidewall RCC completed i. septage tank -final lift completed. j. Sludge holding tank - PCC completed . k. CCT -upto first sidewall completed & work for walkway in progress. l. Chlorine room - upto roof completed, plastering in progress m. Blower room footing work partially pcc completed n pretreatment units pcc partially completed Kollam Project HD
10 May 2022 Sludge holding tank raft steel making work...,Chlorine room parapet wall plastering work in progress Kollam Project HD
09 May 2022 chlorine room parappet wall out side plastering work in progress...,sludge holding tank raft reinforcement work in progress Kollam Project HD
07 May 2022 Equalization tank side wall 2nd lift form work in progress...,pre-treatment unit part pcc work completed...,sludge holding tank raft reinforcement work in progress Kollam Project HD
06 May 2022 Equalization tank side wall 2nd lift form work in progress...,pre-treatment unit earth excavation work in progress...,sludge holding tank raft reinforcement work in progress Kollam Project HD