| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 May 2022 | Equalization tank side wall 2nd lift form work in progress...;MBBR 1 side wall 1st lift form work in progress. | Kollam Project HD | |
| 16 May 2022 | Equalization tank side wall 2nd lift form work in progress...;MBBR 1 side wall 1st lift form work in progress. | Kollam Project HD | |
| 14 May 2022 | MBBR 1 side wall 1st lift form work in progres..,internal road earth cutting work in progress | Kollam Project HD | |
| 13 May 2022 | air blower room footings earth excavation work in progress..,pre-treatment unit part pcc work in progress..,MBBR 1 side wall 1st lift form work in progress | Kollam Project HD | |
| 12 May 2022 | Air blower room footings earth excavation work in progress..,chlorine room parapet wall plastering work in progress...,internal road work started | Kollam Project HD | |
| 11 May 2022 | 57 %completed. All major components first lift RCC completed except MBBR 1,2, ) , sludge holding tank , pretreatment units, centrifuge building,Sludge thickner a. MBBR 3- Second lift RCC completed , b. Sludge thickner - RCC raftcompleted . c. secondary clarifier no.2 - up to sidewall first lift rcc completed d.Secondary clarifier no. 1 - upto sidewall RCC 2.4 m completed. e. MBBR IV - first lift sidewall rcc completed f. MBBR III - second lift sidewall completed . g. MBBR II & I - raft rcc & reinforcement completed, h. equilization tank -sidewall RCC completed i. septage tank -final lift completed. j. Sludge holding tank - PCC completed . k. CCT -upto first sidewall completed & work for walkway in progress. l. Chlorine room - upto roof completed, plastering in progress m. Blower room footing work partially pcc completed n pretreatment units pcc partially completed | Kollam Project HD | |
| 10 May 2022 | Sludge holding tank raft steel making work...,Chlorine room parapet wall plastering work in progress | Kollam Project HD | |
| 09 May 2022 | chlorine room parappet wall out side plastering work in progress...,sludge holding tank raft reinforcement work in progress | Kollam Project HD | |
| 07 May 2022 | Equalization tank side wall 2nd lift form work in progress...,pre-treatment unit part pcc work completed...,sludge holding tank raft reinforcement work in progress | Kollam Project HD | |
| 06 May 2022 | Equalization tank side wall 2nd lift form work in progress...,pre-treatment unit earth excavation work in progress...,sludge holding tank raft reinforcement work in progress | Kollam Project HD |