Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 May 2022 Equalization tank side wall 2nd lift reinforcement work in progress...,pre-treatment unit earth excavation work in progress...,sludge holding tank raft reinforcement work in progress Kollam Project HD
04 May 2022 sludge holding tank raft reinforcement work in progress...,pre-treatment unit earth excavation work in progress...,equalization tank side wall second lift reinforcement work in progress Kollam Project HD
03 May 2022 Sludge holding tank raft form work in progress...,Septage tank side wall final lift form work in progress..,air blower room footings earth excavation work in progress Kollam Project HD
02 May 2022 Air blower room earth excavation work in progress...,Equalization tank side wall deshuttering work & curing work in progress...,Septage tank side wall final lift form work in progress Kollam Project HD
30 Apr 2022 air blower room footings earth excavation work in progress....,sludge holding tank raft pcc completed..,septage tank final lift side wall form work in progres Kollam Project HD
29 Apr 2022 56% completed.Equilization tank side wall rcc completed..sludge holding tank pcc in progress. All major components first lift RCC completed except MBBR 1,2, equilization tank ( ready for sidewall rcc in this week ) , Sludge thickner a. MBBR 3- Second lift RCC in progress b. Sludge thickner - RCC completed. c.secondary clarifier no.2 - up to sidewall first lift rcc completed. d.Secondary clarifier no. 1 - upto sidewall RCC 2.4 m completed. e. MBBR IV - first lift sidewall rcc completed f. MBBR III - second lift sidewall in progress. g. MBBR II & I - raft rcc & reinforcement completed, h.equilization tank -sidewall form work in progress i. Sludge holding tank excavation completed and pcc planed today j. CCT -upto first sidewall completed & work for walkway in progress. k.Chlorine room - upto roof completed, plastering in progress l. Blower room footings earth excavation work in progress Kollam Project HD
28 Apr 2022 55% completed. Work for RCC for equilization tank is scheduled today and sludge holding tank pcc in progress. All major components first lift RCC completed except MBBR 1,2, equilization tank ( ready for sidewall rcc in this week ) , Sludge thickner a. MBBR 3- Second lift RCC in progress, b. Sludge thickner - RCC completed. c.secondary clarifier no.2 - up to sidewall first lift rcc completed d.Secondary clarifier no. 1 - upto sidewall RCC 2.4 m completed. e. MBBR IV - first lift sidewall rcc completed f. MBBR III - second lift sidewall in progress. g. MBBR II & I - raft rcc & reinforcement completed, h.equilization tank -sidewall form work in progress i. septage tank - upto second lift sidewall completed, final lift scheduled today.. j. Sludge holding tank excavation completed and ready for PCC. k. CCT -upto first sidewall completed & work for walkway in progress. l. Chlorine room - upto roof completed, plastering in progress m. Blower room position revised as per revised layout Kollam Project HD
26 Apr 2022 Equilization tank side wall ready for concrete..,Air blower room earth excavation work in progress...,sludge holding tank de-watering for pcc. Kollam Project HD
21 Apr 2022 Equilization tank side wall form work in progress..MBBR 3 side wall 2nd lift de-shuttering work in progress....Compound wall primer coating work in progress...Air blower room earth excavation work started... Kollam Project HD
20 Apr 2022 54% completed. All major components first lift RCC completed except MBBR 1,2, equilization tank ( ready for sidewall rcc in this week ) , Sludge thickner a. MBBR 3- Second lift RCC in progress, b. Sludge thickner - RCC completed. c.secondary clarifier no.2 - up to sidewall first lift rcc completed d.Secondary clarifier no. 1 - upto sidewall RCC 2.4 m completed. e. MBBR IV - first lift sidewall rcc completed f. MBBR III - second lift sidewall in progress. g. MBBR II & I - raft rcc & reinforcement completed, h.equilization tank -sidewall form work in progress i. septage tank - upto second lift sidewall completed, final lift scheduled today.. j. Sludge holding tank excavation completed and ready for PCC. k. CCT -upto first sidewall completed & work for walkway in progress. l. Chlorine room - upto roof completed, plastering in progress m. Blower room position revised as per revised layout Kollam Project HD