| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 May 2022 | Equalization tank side wall 2nd lift reinforcement work in progress...,pre-treatment unit earth excavation work in progress...,sludge holding tank raft reinforcement work in progress | Kollam Project HD | |
| 04 May 2022 | sludge holding tank raft reinforcement work in progress...,pre-treatment unit earth excavation work in progress...,equalization tank side wall second lift reinforcement work in progress | Kollam Project HD | |
| 03 May 2022 | Sludge holding tank raft form work in progress...,Septage tank side wall final lift form work in progress..,air blower room footings earth excavation work in progress | Kollam Project HD | |
| 02 May 2022 | Air blower room earth excavation work in progress...,Equalization tank side wall deshuttering work & curing work in progress...,Septage tank side wall final lift form work in progress | Kollam Project HD | |
| 30 Apr 2022 | air blower room footings earth excavation work in progress....,sludge holding tank raft pcc completed..,septage tank final lift side wall form work in progres | Kollam Project HD | |
| 29 Apr 2022 | 56% completed.Equilization tank side wall rcc completed..sludge holding tank pcc in progress. All major components first lift RCC completed except MBBR 1,2, equilization tank ( ready for sidewall rcc in this week ) , Sludge thickner a. MBBR 3- Second lift RCC in progress b. Sludge thickner - RCC completed. c.secondary clarifier no.2 - up to sidewall first lift rcc completed. d.Secondary clarifier no. 1 - upto sidewall RCC 2.4 m completed. e. MBBR IV - first lift sidewall rcc completed f. MBBR III - second lift sidewall in progress. g. MBBR II & I - raft rcc & reinforcement completed, h.equilization tank -sidewall form work in progress i. Sludge holding tank excavation completed and pcc planed today j. CCT -upto first sidewall completed & work for walkway in progress. k.Chlorine room - upto roof completed, plastering in progress l. Blower room footings earth excavation work in progress | Kollam Project HD | |
| 28 Apr 2022 | 55% completed. Work for RCC for equilization tank is scheduled today and sludge holding tank pcc in progress. All major components first lift RCC completed except MBBR 1,2, equilization tank ( ready for sidewall rcc in this week ) , Sludge thickner a. MBBR 3- Second lift RCC in progress, b. Sludge thickner - RCC completed. c.secondary clarifier no.2 - up to sidewall first lift rcc completed d.Secondary clarifier no. 1 - upto sidewall RCC 2.4 m completed. e. MBBR IV - first lift sidewall rcc completed f. MBBR III - second lift sidewall in progress. g. MBBR II & I - raft rcc & reinforcement completed, h.equilization tank -sidewall form work in progress i. septage tank - upto second lift sidewall completed, final lift scheduled today.. j. Sludge holding tank excavation completed and ready for PCC. k. CCT -upto first sidewall completed & work for walkway in progress. l. Chlorine room - upto roof completed, plastering in progress m. Blower room position revised as per revised layout | Kollam Project HD | |
| 26 Apr 2022 | Equilization tank side wall ready for concrete..,Air blower room earth excavation work in progress...,sludge holding tank de-watering for pcc. | Kollam Project HD | |
| 21 Apr 2022 | Equilization tank side wall form work in progress..MBBR 3 side wall 2nd lift de-shuttering work in progress....Compound wall primer coating work in progress...Air blower room earth excavation work started... | Kollam Project HD | |
| 20 Apr 2022 | 54% completed. All major components first lift RCC completed except MBBR 1,2, equilization tank ( ready for sidewall rcc in this week ) , Sludge thickner a. MBBR 3- Second lift RCC in progress, b. Sludge thickner - RCC completed. c.secondary clarifier no.2 - up to sidewall first lift rcc completed d.Secondary clarifier no. 1 - upto sidewall RCC 2.4 m completed. e. MBBR IV - first lift sidewall rcc completed f. MBBR III - second lift sidewall in progress. g. MBBR II & I - raft rcc & reinforcement completed, h.equilization tank -sidewall form work in progress i. septage tank - upto second lift sidewall completed, final lift scheduled today.. j. Sludge holding tank excavation completed and ready for PCC. k. CCT -upto first sidewall completed & work for walkway in progress. l. Chlorine room - upto roof completed, plastering in progress m. Blower room position revised as per revised layout | Kollam Project HD |