Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Jul 2022 1.Pre-treatment unit - Raft reinforcement work in progress. 2.Sludge holding tank - Raft reinforcement work in progress. 3.Air blower room - Plinth PCC work completed (plinth beam steel making work in progress) 4.Sludge shed - Footing & column reinforcement work in progress Kollam Project HD
13 Jul 2022 1.Pre-treatment unit - Raft reinforcement work in progress. 2.Sludge holding tank - Raft reinforcement work in progress. 3.Air blower room - Plinth bottom earth leveling & compaction work in progress(for pcc) 4.Sludge shed - Footing & column setting out work in progress Kollam Project HD
12 Jul 2022 Pre-treatment unit raft reinforcement work in progress...,Sludge holding tank raft reinforcement work in progress..,Clarifier control chamber raft reinforcement work in progress...,MBBR 1 inside chamber form work in progress.. Kollam Project HD
12 Jul 2022 Patment unit raft reinforcement work in progress...,Sludge holding tank raft reinforcement work in progress..,Clarifier control chamber raft reinforcement work in progress...,MBBR 1 inside chamber form work in progress..re-tre Kollam Project HD
11 Jul 2022 Sludge holding tank raft reinforcement work in progress..,Clarifier control chamber raft reinforcement work in progress...,MBBR 1 inside chamber form work in progress..'sludge shed part footings earth excavation work in progress Kollam Project HD
09 Jul 2022 pre-treatment unit raft reinforcement work in progress..,sludge holding tank raft reinforcement work in progress Kollam Project HD
08 Jul 2022 MBBR 2 side wall second lift getting ready for concrete..,sludge thickner side wall & thickned sludge sump ready for concrete..,pre-treatment unit raft reinforcement work in progress..,sludge holding tank raft reinforcement work in progress Kollam Project HD
07 Jul 2022 Pre- treatment unit raft steel work..MBBR II side wall second lift form work...sludge holding tank raft reinforcement work...Air blower room footings earth filling work.. Kollam Project HD
05 Jul 2022 Sludge thickner side wall form work in progress...,pre-treatment unit setting out work in progress..,MBBR 2 side wall second lift form work in progress. Kollam Project HD
04 Jul 2022 Sludge thickner side wall form work in progress..,Sludge holding tank raft reinforcement work in progress..,MBBR 2 side wall second lift form work in progress....,pre treatment unit raft steel making work in progress Kollam Project HD